The Tri An Hydropower Plant Expansion Project has reclaimed 73% of the land area.

According to the report of the Department of Industry and Trade, the Tri An Hydropower Plant Expansion Project in Vinh Cuu District has so far approved the compensation and land acquisition plan for 67/92 hectares, reaching about 73% of the land area to be acquired for the project. The remaining area is land that has not been compensated; the Provincial People's Committee has directed the Vinh Cuu District People's Committee to urgently complete the determination of specific land prices, price application, and development of compensation, support, and resettlement plans this June.

Báo Đồng NaiBáo Đồng Nai25/06/2025

The Vinh Cuu District Land Fund Development Center has handed over nearly 22 hectares of land. It is expected that by June 30, compensation will be completed and the land will be handed over for about 65/92 hectares, equivalent to about 70% of the total land area to be recovered.

The Tri An Hydropower Plant Expansion Project, invested by Vietnam Electricity Group, has a total installed capacity of 200 MW and is expected to start construction on the occasion of National Day, September 2. In particular, the Hieu Liem Bridge project will start construction from December 29, 2024.

HL

Source: https://baodongnai.com.vn/kinh-te/202506/du-an-nha-may-thuy-dien-tri-an-mo-rong-da-thu-hoi-73-dien-tich-dat-80e13e5/


Comment (0)

No data
No data

Same tag

Same category

Western tourists enjoy buying Mid-Autumn Festival toys on Hang Ma Street to give to their children and grandchildren.
Hang Ma Street is brilliant with Mid-Autumn colors, young people are excitedly checking in non-stop
Historical message: Vinh Nghiem Pagoda woodblocks - documentary heritage of humanity
Admiring Gia Lai coastal wind power fields hidden in the clouds

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;