The project is currently implementing the construction of the main part of the building. When completed, the Phu Tho Circus and Multi-purpose Performance Hall will be both a performance venue and an art training center, organizing cultural and sports events - Photo: PHUONG NHI
It is expected that on April 30, 2025, Phu Tho Circus and Multi-purpose Performance Center (District 11) will be inaugurated and have its first show. This is the request of Chairman of Ho Chi Minh City People's Committee Phan Van Mai during the project site inspection on February 17.
At the same time, the city chairman assigned the units to calculate that from the inauguration date until the end of 2025, tickets to performances can be free for some groups of people such as children and the disadvantaged. The city will allocate the investment budget for performing units during this period.
The project to build a multi-purpose circus and performance theater in Phu Tho started construction at the end of April 2023, with a total investment of nearly 1,400 billion VND.
The project has a scale of 2,000 seats and a 300-seat multi-purpose training room, with auditoriums, stages, practice rooms, circus animal training and breeding areas, restaurants...
This is one of 50 key projects of the city to celebrate the 50th anniversary of national reunification.
The project is also expected to be one of the typical new cultural institutions of the city named after Uncle Ho.
Some pictures of Phu Tho circus and multi-purpose performance:
The total floor area of the circus is over 31,600 square meters. This is a level 1 cultural civil work - Photo: CAM NUONG
The Phu Tho circus and multi-purpose performance building project has 2 underground floors; the circus and multi-purpose performance block has 12 above-ground floors; the administrative, service, and restaurant block has 2 above-ground floors - Photo: CAM NUONG
On the morning of February 17, Chairman of the City People's Committee Phan Van Mai inspected the project's progress - Photo: PHUONG NHI
In 2023, the project was allocated capital of 290 billion VND, of which nearly 180 billion VND (62%) was disbursed. In 2024, the project was assigned more than 558 billion VND. The Ho Chi Minh City Management Board of Civil and Industrial Construction Investment Projects (investor) strives to achieve a disbursement rate of over 95% - Photo: PHUONG NHI
The main circus building (12 floors, area of nearly 4,000m2) has completed the concrete work of the basement floor and 5th floor, columns and walls from 5th floor to 6th floor. The contractor is implementing the construction and installation of the steel structure system for floors 6, 7 and 8 - Photo: PHUONG NHI
According to the plan, the circus block will complete the rough construction on September 2, 2024 and complete the project in February 2025, then test the operation and accept it for use on April 30, 2025 - Photo: PHUONG NHI
For the 2,000-seat stage, the contractor has ordered essential equipment from foreign manufacturers. The contractor ensures that the import and installation are carried out in sync with the construction progress - Photo: PHUONG NHI
Phu Tho Circus and Multi-Purpose Performance Theater is located on Lu Gia Street (District 11), next to Phu Tho Stadium - Graphics: PHUONG NHI
Source
Comment (0)