Urgently overcome the impact of storms and rains at some locations of Tuyen Quang - Phu Tho highway

Việt NamViệt Nam08/07/2024


Construction unit to reinforce drainage ditches of Tuyen Quang - Phu Tho highway.

Immediately after grasping the situation, the Provincial Traffic Construction Investment Project Management Board (project investor) inspected the scene, strongly directed the construction contractors, urgently mobilized human resources, machinery, design consultants, supervision consultants, and implemented measures to overcome the consequences caused by the storm.

Construction unit for negative slope reinforcement of Tuyen Quang - Phu Tho expressway.

Along with that, the Management Board urged contractors to speed up the construction progress to complete all remaining work items inside and outside the main route, renovate guardrails, kilometer posts, signs; add water barriers; reinforce longitudinal ditches by assembling cement concrete panels; repair and fill, compact at negative slopes, manhole locations for longitudinal ditches; clean up ditches, cross-roads of residential tunnels, upstream and downstream of culverts, rocks and soil that have slid down into people's rice fields, ponds, lakes, etc. to report to competent authorities to organize inspections to allow acceptance, handover and put the Project into use and official exploitation, expected to be completed in July 2024.



Source: https://baotuyenquang.com.vn/khan-truong-khac-phu-tho-anh-huong-do-mua-bao-tai-mot-so-vi-tri-cua-cao-toc-tuyen-quang-phu-tho-194660.html

Comment (0)

No data
No data

Same tag

Same category

Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;