Lam Dong attaches responsibility to leaders with project progress

The investor coordinates with relevant parties and localities to speed up the progress of major projects to serve the development needs of the province.

Báo Lâm ĐồngBáo Lâm Đồng26/09/2025

On September 26, Lam Dong Provincial People's Committee held a meeting to listen to reports on the implementation of tasks and progress of projects invested by the Management Board of Construction Investment Project No. 3 (old Dak Nong area); the implementation of site clearance for the North-South Expressway Construction Investment Project, West section, Gia Nghia-Chon Thanh (section through Lam Dong province).

_dsc4847(1).jpg
Lam Dong Provincial People's Committee held a meeting to listen to reports on the implementation of tasks and progress of projects invested by Construction Investment Project Management Board No. 3.

Comrade Le Trong Yen, Member of the Provincial Party Standing Committee, Vice Chairman of Lam Dong Provincial People's Committee chaired the conference.

_dsc4911(1).jpg
Comrade Le Trong Yen, Member of the Provincial Party Standing Committee, Vice Chairman of Lam Dong Provincial People's Committee chaired the Conference.

According to the report of the Investment and Construction Project Management Board No. 3, the unit is the investor of 36 projects; of which, 2 projects are preparing for investment, 24 projects are under construction, 10 projects are being completed and put into use. In addition, there are 2 projects under the Investment Project for Construction of the North-South Expressway, West, Gia Nghia-Chon Thanh section.

_dsc4863.jpg
Director of the Management Board of Construction Investment Project No. 3, Ha Sy Son, said the main difficulty and obstacle of projects in the area at present is site clearance.

Up to now, the capital allocated for 2025 has been disbursed over 332.9 billion VND/2,200 billion VND, reaching 15% of the plan. Currently, the Board is still facing many difficulties due to problems in site clearance, especially in terms of implementing units, procedures for measuring and accepting maps. Some projects have difficulty in terms of source of fill materials, overlapping with bauxite exploration and exploitation planning...

Particularly for the North-South Expressway Construction Investment Project in the West, the Gia Nghia-Chon Thanh section is about 23.1km long, with 3 component projects. The total area of ​​land cleared is about 227.5ha, located in the two communes of Kien Duc and Quang Tin. According to the general assessment, this project is currently behind schedule.

mb1.jpg
Component project 2 (under the Expressway Project) on investment in service roads and overpasses, the investor has disbursed over 37.4% of capital.

Specifically, up to now, Component Project 1, implemented by Gia Nghia-Chon Thanh Expressway Company Limited, is organizing the preparation of design documents. Component Project 2 on investment in service roads and overpasses, the investor has disbursed over 37.4% of capital. Component Project 4 on compensation and resettlement support, the investor has set up markers in the field, and is speeding up the field reconciliation...

At the working session, representatives of departments, branches, units and localities raised the implementation situation, difficulties and problems, as well as proposed ways to increase work progress.

_dsc4894-1-.jpg
Deputy Director of the Department of Construction Phan Nhat Thanh proposed that the province assign the Department of Construction to take the lead in synthesizing results and periodically urging relevant parties.

The leaders of the Department of Construction said that the general progress of projects managed by the Project Management Board is generally slow, with low capital disbursement. The Department of Construction proposed to preside over the synthesis of results and periodically urge relevant parties. In particular, it emphasized the coordination, specific progress of the parties, professional personnel work, and high responsibility to complete on schedule and effectively.

_dsc4875(1).jpg
Mr. Nguyen Van Sang, Chairman of the People's Committee of Quang Tin commune, said that the locality is facing difficulties in resettlement for the North-South Expressway Project, West section, Gia Nghia - Chon Thanh, through Lam Dong province.

According to the leaders of Quang Tin commune, the locality has a huge amount of work related to the expressway project, both in terms of site clearance and resettlement for the people. The commune is also facing difficulties in determining the specific area and form of resettlement for the people, whether it is on-site or mobilizing households to move to the land area that has been cleared after the reclamation of bauxite mining.

_dsc4881(1).jpg
A representative of Dak Nong Aluminum Company - TKV said that the company is speeding up coordination with localities, departments and branches to resolve problems related to overlapping bauxite planning in the expressway project area.

According to the representative of Dak Nong Aluminum Company - TKV, the company is currently accelerating coordination with localities and departments to resolve problems related to overlapping bauxite planning in the expressway project area. The roadmap of the Vietnam National Coal - Mineral Industries Group is to reclaim 10 hectares of the expressway in the fourth quarter of 2025 and 5 hectares in October 2025. Before March 2026, the entire land for the expressway project will be available.

_dsc4909(1).jpg
Deputy Head of the Dong Nai Province Construction Investment Project Management Board, Duong Hoang Anh Toan, said that the province has done a good job of propagating and mobilizing people to ensure progress for the expressway project.

Deputy Head of the Dong Nai Province Construction Investment Project Management Board, Duong Hoang Anh Toan, said that on the local side, the progress of work related to the expressway project is basically on schedule; in which, site clearance is done well. The local experience is to consider site clearance as the first and important step. Therefore, the province actively mobilizes people to agree and support the implementation in a rolling form, easy to do first, especially focusing on resettlement.

z7052147472481_c5bde902f497631e7c86be287c31715a.jpg
Comrade Le Trong Yen, Member of the Provincial Party Standing Committee, Vice Chairman of Lam Dong Provincial People's Committee requested relevant parties to perform their tasks with the spirit of "6 clear" in accordance with the direction of the Prime Minister.

Concluding the working session, comrade Le Trong Yen requested that relevant parties, People's Committees of communes and wards and investors carry out their tasks with the spirit of "6 clear": clear people, clear work, clear responsibility, clear time, clear process, clear efficiency; thoroughly implement the motto: "Only discuss doing, not backtracking". All difficulties and problems must be resolved decisively, without pushing or avoiding.

Do not give reasons for delay or problems due to the improvement of personnel work in departments and localities, because the legal documents are complete. The investor coordinates with consulting units, centers, departments and branches to speed up the work. The parties must be attached to specific responsibilities and progress.

Vice Chairman of the Provincial People's Committee Le Trong Yen proposed

Project Management Board No. 3 needs to speed up work efficiency and increase the rate of investment capital disbursement. Kien Duc and Quang Tin communes should promote the leadership role of the Party, mobilize the participation of the entire political system, and focus on promoting the correct and complete inventory of assets on land. At the same time, propagate and mobilize people to create consensus to speed up site clearance and facilitate the project.

Source: https://baolamdong.vn/lam-dong-gan-trach-nhiem-nguoi-dung-dau-voi-tien-do-cac-du-an-393245.html


Comment (0)

No data
No data

Same tag

Same category

Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory
Tò he – from a childhood gift to a million-dollar work of art

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;