Contractor proposes early handover of construction site for National Highway 14E

Việt NamViệt Nam30/04/2024

z5378093304974_662aa0f807b94339b7d2b1ecbf3b58c0.jpg
On the left side of National Highway 14E, the section from km17+590 to km17+700 through Binh Quy commune cannot be constructed because the people have not agreed to hand over the site. Photo: NB

Package XD01 (route km15+270-km40+00) was awarded the construction contract by the consortium of 168 Vietnam Construction Group Joint Stock Company and Dong Thuan Ha Company Limited. The package is located in the two districts of Thang Binh and Hiep Duc. In which, the consortium member is Dong Thuan Ha Company Limited (headquartered in Tay Ninh province) undertaking the construction of the section km15+270 - km27+314.69 through Thang Binh district.

Dong Thuan Ha Enterprise said that up to now, the contractor has basically completed the installation of U-groove components, and the expansion of the road surface to the old road surface elevation of the sections that have been handed over and have the consent of the people. However, in general, the contractor has not been able to synchronously implement the construction of the items to ensure the contract progress and construction methods approved by Project Management Board 4 (Vietnam Road Administration), the unit assigned to manage the project.

2(2).jpg
The contractor is currently stripping the soil to construct the roadbed, the section from km15+800 to km15+900 (Binh Quy commune) was just handed over on April 26. Photo: CT

The main reason is the slow handover of the site, not to mention the area of ​​the handed over site is still intermittent and not continuous. In addition, the locations where the site has been handed over are still stuck with technical infrastructure systems due to slow relocation (clean water supply system).

Accordingly, Binh Quy commune has handed over 10 sections that can be constructed with a total length of 0.737m/4.9km, while 7 sections with a total length of 0.635m cannot be constructed because people have not agreed to hand over the site.

On April 26, Thang Binh district continued to hand over an additional 100m long section of land on the left side of the route, opposite the entrance to Ha Lam intersection of the Da Nang - Quang Ngai expressway (the previously compensated section of the expressway).

3(1).jpg
The contractor cannot construct the section from km22+600 to km22+700 on the right side of the route (Binh Tri commune) because the people have not agreed to hand over the site. Photo: NB

Binh Dinh Bac commune has handed over 6 sections with a total length of 2.088/3.1km that can be constructed; 2 sections with a total length of 0.205m cannot be constructed because the people have not agreed to hand over the site.

Binh Tri Commune has handed over 22 sections of land that can be constructed with a total length of 3.18/5.2km; 7 sections with a total length of 0.939m cannot be constructed yet because the people have not agreed to hand over the land.

With the above reality, the contractor has just sent a document to Project Management Board 4 (and also to the Vietnam Road Administration and the People's Committee of Thang Binh district) requesting attention and early handover of the site so that the contractor can continue construction, not affecting the progress and causing damage to the contractor due to lack of site. Considering the delay in handing over the site is the basis for extending the progress of the contract implementation of package XD01.


Source

Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;