Strive to complete the Hoa Lien - Tuy Loan expressway in October 2025

The service road on both sides of the Hoa Lien - Tuy Loan expressway is still under construction and faces many difficulties. Therefore, the Department of Construction has issued many documents urging the Ho Chi Minh Road Project Management Board to focus on completing the service road in October 2025 to serve the travel needs of the people.

Báo Đà NẵngBáo Đà Nẵng24/09/2025

z7016547456118_ed78abd3cad1c1427cdcaf4a8898e82e.jpg
Construction of service road. Photo: GIA MINH

According to the reporter's investigation, 20.2km of service roads and crossroads are still obstructed by houses and structures of local residents, and some households have been compensated but have not yet relocated. Da Nang City has directed the People's Committees of communes to focus on resolving the problems to hand over the clean site to the contractor to complete the construction of service roads, crossroads, highway fences, etc.

The Department of Construction requested the Ho Chi Minh Road Project Management Board to continue to closely coordinate with the locality to continue to review the problems between reality and design to make adjustments if necessary, organize the construction neatly, complete each item and ensure environmental sanitation, labor safety, traffic safety to minimize problems affecting people's lives.

z7016551358776_8d2f11b21670cf0045a7e8cdc13f387f.jpg
The contractor is focusing on construction, striving to complete in 2025. Photo: GIA MINH

It is known that during the construction process, the Ho Chi Minh Road Project Management Board presided over and coordinated with the People's Committee of Hoa Khanh Ward and related units to regularly inspect the site to remove obstacles in the site. Thereby, directing the contractor to develop a reasonable construction plan, minimizing the impact on people's lives. At the same time, strengthen the inspection of traffic safety, environmental sanitation, improve the drainage system, promptly handle existing problems according to feedback, listen to people's opinions, have appropriate solutions, and ensure absolute safety during the construction process.

According to the report of the Ho Chi Minh Road Project Management Board, in Phu Thuong village (Hoa Khanh ward), the contractor is focusing on constructing the cross-road section connecting from the underpass (next to Trung bridge) to the parallel service road on both sides of the route. Up to now, the contractor has completed the construction of the roadbed, filling up the entire gravel layer of the connecting route to facilitate people's traffic; the road surface and drainage system will be completed in September 2025.

z7016548792454_24a88f6c2ae4880260310ac250530425.jpg
Hoa Lien - Tuy Loan Expressway was technically opened to traffic on August 19. Photo: GIA MINH

Currently, there are still some telecommunication cables (not power lines) in the underpass. The Ho Chi Minh Road Project Management Board requests the city leaders, the Department of Construction, and related units to pay attention to creating favorable conditions for contractors to organize construction and complete the route...

Source: https://baodanang.vn/phan-dau-hoan-thanh-tuyen-duong-gom-cao-toc-hoa-lien-tuy-loan-trong-thang-10-2025-3303490.html


Comment (0)

No data
No data

Same tag

Same category

Admiring Gia Lai coastal wind power fields hidden in the clouds
Coffee shops in Hanoi are bustling with Mid-Autumn Festival decorations, attracting many young people to experience
Vietnam's 'sea turtle capital' recognized internationally
Opening of the art photography exhibition 'Colors of life of Vietnamese ethnic groups'

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product