Close-up of the seriously degraded coastal road worth more than 2,000 billion VND in Ha Tinh
Wednesday, October 9, 2024 10:00 AM (GMT+7)
The coastal road in Ha Tinh province with a total investment of more than 2,000 billion VND, 120 km long, is seriously degraded, with many potholes, posing a potential risk of traffic accidents.
Clip: The coastal road worth more than 2,000 billion in Ha Tinh is seriously degraded.
The Ha Tinh coastal route is 120 km long, starting from Cua Hoi bridge (Nghi Xuan district) to the intersection with National Highway 12C at Vung Ang port (Ky Anh town). The traffic route passes through 6 localities such as Nghi Xuan, Loc Ha, Thach Ha, Cam Xuyen, Ky Anh and Ky Anh town (Ha Tinh province).
The 33 km coastal route of Ha Tinh overlaps with some invested sections of projects in 3 localities (Loc Ha, Thach Ha and Ky Anh town), and the remaining 87 km is newly built in 2 phases (the investor of phase 1 is the Ha Tinh Department of Transport, and phase 2 is the Provincial Traffic Project Management Board) with a total investment of more than 2,000 billion VND, from the central budget and part of the Ha Tinh budget.
The section from Cam Linh commune (Cam Xuyen district) to Ky Bac commune (Ky Anh district) is about 6 km long, put into operation and used for 7 years, but has peeling and dents on the road surface.
According to local residents, this road has been degraded many times but the management unit only made temporary repairs. After a short time of use, the road continued to deteriorate.
The peeling and rutting marks form large holes, while the number of trucks carrying materials is constantly running, which is very dangerous. If the driver is not familiar with it, driving at night will potentially pose a safety risk.
Some locations where heavy trucks frequently travel have created ruts about 20 cm deep.
Talking to Dan Viet reporter, Mr. Tran Van Tung - Director of the Management Board of Traffic Construction Investment Project of Ha Tinh province, said: "The road has been in use for a long time, when damaged, the unit has also temporarily repaired the damaged locations many times. Currently, we are in the stage of selecting a contractor."
"After the appraisal and approval, we will submit a bidding plan and proceed to select a construction unit. In the coming time, we will thoroughly repair and proceed to lay two layers of asphalt concrete," said Mr. Tran Van Tung - Director of the Management Board of Traffic Construction Investment Projects of Ha Tinh province.