What is the cause of the slow progress of Bach Mai and Viet Duc Hospital projects?

Báo Kinh tế và Đô thịBáo Kinh tế và Đô thị17/06/2024


On the afternoon of June 17, at a press meeting to provide medical information for the second quarter of 2024, Minister of Health Dao Hong Lan said that the Ministry has reviewed and removed difficulties and obstacles and promoted the implementation of the investment project to build the second facility of Bach Mai Hospital and Viet Duc Friendship Hospital in Ha Nam province.

Accordingly, the second facility of Bach Mai Hospital and Viet Duc Friendship Hospital both have a scale of 1,000 beds/hospital with a total investment of more than 4,500 billion VND for each facility. These are facilities built with the aim of reducing the need for medical examination and treatment for the overloaded first facility in Hanoi .

Bach Mai Hospital, branch 2. Photo: Internet source
Bach Mai Hospital, branch 2. Photo: Internet source

On October 21, 2018, the examination areas of both facilities were inaugurated. However, for nearly 6 years, Viet Duc Friendship Hospital, Facility 2, has only stopped at the ribbon cutting ceremony and has never received any patients.

According to the Ministry of Health , the reason for the slow progress is that it has not fully anticipated the problems that arise during the implementation process, especially the implementation of regulations in basic construction investment and the implementation of construction contracts. Therefore, problems have arisen in payment, settlement, and capital disbursement...

Currently, the Ministry of Health is coordinating with the Ministry of Construction to propose mechanisms to resolve problems, such as adjusting contract terms and inappropriate issues during implementation to ensure a legal basis.

Previously, for the two projects of Bach Mai Hospital and Viet Duc Friendship Hospital, the Ministry of Health approved the adjustment of the project implementation time until December 31, 2024 and directed the investor to work with contractors to continue construction and complete the project.



Source: https://kinhtedothi.vn/cham-tien-do-du-an-benh-vien-bach-mai-va-viet-duc-nguyen-nhan-do-dau.html

Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;