Quang Ngai Chairman requests that the Quang Ngai - Hoai Nhon expressway must be opened by August 30.

Regarding the difficulties of the Quang Ngai - Hoai Nhon Expressway Project, the Chairman of the Quang Ngai Provincial People's Committee directed the units to resolve them, and at the same time requested to speed up the progress, to open the route by August 30 at the latest.

Báo Đầu tưBáo Đầu tư29/12/2024

On August 6, Chairman of the People's Committee of Quang Ngai province Nguyen Hoang Giang chaired a working session with units and localities to direct the removal of a number of obstacles related to the Quang Ngai - Hoai Nhon section project, part of the North - South expressway construction project in the east, phase 2021 - 2025.

Accordingly, the Quang Ngai - Hoai Nhon component project has a length of 88km, of which the section passing through Quang Ngai province is 60.3km long. Up to now, the main items have been basically completed such as roadbed filling, tunnel No. 1 and tunnel No. 2 construction. Of the total 77 bridges on the route, 70 bridges have had girders installed and are under bridge deck construction. The project is entering the finishing stage, the remaining workload is not large. To ensure progress, contractors have mobilized 3,450 engineers, workers and more than 1,400 machines and equipment. However, the overall progress is still affected by some problems in compensation and site clearance at 7 locations in the overpass and intersection packages...

Chairman of Quang Ngai Provincial People's Committee Nguyen Hoang Giang inspected the Quang Ngai - Hoai Nhon expressway project.

Mr. Nguyen Hoang Giang, Chairman of the People's Committee of Quang Ngai province, said that currently the remaining workload is very little, but he requested the forces, commune authorities, investors, and contractors to continue to promote the spirit of solidarity and high unity, join together to speed up the construction progress, and commit to open the route no later than August 30.

Mr. Nguyen Hoang Giang requested the chairmen of the People's Committees of the communes and wards concerned to clearly define the common goal, consider this an important political task, concentrate resources, promote the sense of responsibility, and be determined in directing and operating. Besides, it is necessary to be close to the people, strengthen propaganda and mobilization work so that people understand and share. At the same time, it is necessary to publicly and transparently disclose the plan, the extent of damage, compensation and have a specific commitment with the people to create consensus and support. Localities should promptly support the construction unit to complete the project on schedule according to the requirements of the Government, the Prime Minister and the province.

Construction units of the Quang Ngai - Hoai Nhon Expressway Project are speeding up progress to finish earlier than expected.

Immediately after the meeting, Chairman of the Provincial People's Committee Nguyen Hoang Giang and leaders of departments, branches and localities directly inspected the construction sites that affected people's houses due to vibrations from the roller. Mr. Nguyen Hoang Giang requested the construction unit to urgently review and fully assess the impact during the construction process and promptly make final compensation payments to affected households.

Source: https://baodautu.vn/chu-tich-quang-ngai-yeu-cau-den-308-phai-thong-tuyen-cao-toc-quang-ngai---hoai-nhon-d351612.html


Comment (0)

No data
No data

Same tag

Same category

Admiring Gia Lai coastal wind power fields hidden in the clouds
Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;