The project of over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape.

Báo Tiền PhongBáo Tiền Phong03/07/2024

TPO - The traffic infrastructure project at the gateway to Tan Son Nhat airport is being accelerated with items such as expanding Hoang Hoa Tham street, building connecting routes and the Tran Quoc Hoan - Cong Hoa underpass to be completed by the end of 2024.
The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 1

The project to build a road connecting Tran Quoc Hoan - Cong Hoa through the airport land to relieve traffic congestion and connect to Terminal T3 of Tan Son Nhat airport is gradually taking shape after nearly two years of construction.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 2

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (investor), the entire Tran Quoc Hoan - Cong Hoa connecting road project has reached more than 50% of the volume, expected to be completed by the end of 2024.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 3

The connecting road is 25 - 48m wide with 6 lanes, maximum speed of 50 km/h, total investment capital of more than 4,800 billion VND.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 4

The contractor is speeding up the construction of technical infrastructure items such as drainage, lighting, and sidewalks to complete on schedule.

The project costing more than 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 5

The construction of the road connecting Tran Quoc Hoan to Cong Hoa Street is revealed with a 6-lane wide road surface.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 6

Another section at the end of the project is also under busy construction, the area is still located within national defense land.

The project costing more than 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 7

The underpass at the intersection of Tran Quoc Hoan - Phan Thuc Duyen (Ward 2, Tan Binh District) is package number 9 of the project connecting Tran Quoc Hoan Street to Cong Hoa Street through Tan Son Nhat Airport land.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 8

At the starting point of the project, adjacent to Cong Hoa Street, the roadbed of a nearly 500m long section has been completed, running parallel to C12 Street.

The project costing more than 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 9

According to Tien Phong, compared to half a year ago, about 500m at the beginning of the road adjacent to the Truong Chinh - Cong Hoa train station has been paved, forming a lane divider.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 10

According to Mr. Luong Minh Phuc - Director of the HCM City Traffic Construction Investment Project Management Board, the Tran Quoc Hoan - Phan Thuc Duyen underpass project has reached more than 80% of its volume and is expected to be completed in August.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 11

The upcoming project will build another underpass at the Truong Chinh - Tan Ky Tan Quy intersection. The entire project is currently more than 50% complete and is expected to be completed by the end of this year.

The project costing over 5,000 billion VND to 'rescue' Tan Son Nhat International Airport has revealed its shape, photo 12

The projects connecting Tran Quoc Hoan - Cong Hoa and expanding Hoang Hoa Tham Street, when put into operation, will contribute to completing the traffic infrastructure system and reducing traffic congestion in the Tan Son Nhat International Airport area. In particular, these projects are to synchronize with the T3 Passenger Terminal with a capacity of 20 million passengers/year, which will be put into operation in the near future.

Source: https://tienphong.vn/cong-trinh-hon-5000-ty-dong-giai-cuu-san-bay-quoc-te-tan-son-nhat-lo-hinh-hai-post1651068.tpo

Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;