According to Engineer Nguyen Duc Tung, Site Commander - Thang Long Project Management Board, currently all items of the intersections have completed investment items and it is expected that by April 19, 2024, the Thieu Giang and Dong Thang intersections on Mai Son Expressway - National Highway 45 will be put into operation, creating favorable conditions for people to travel on the occasion of April 30 and May 1.
Dong Thang Interchange (Trieu Son) started construction on July 21, 2023, basically completed, ready to be put into use.
From Dong Thang intersection, people go to Thanh Hoa city center about 10km; go to Sam Son beach tourist area or to Tho Xuan airport about 26km...
Thieu Giang Interchange (Thieu Hoa) belongs to Sub-project 2 - Road project connecting National Highway 1 with National Highway 45. This sub-project has a section from the beginning of the Ma River overpass to the intersection with National Highway 45, Km 7+250 - Km 14+603.
Up to now, the items of the Thieu Giang intersection project have been basically completed. According to the plan, the intersection will be put into use by April 19, 2024, creating favorable conditions for people to travel on the occasion of April 30 and May 1.
Iron fence system and power grid of the intersection have been completed.
The system of signs, median strips, and lane markings of intersections has been completed.
Workers are urgently planting grass to prevent landslides on the slopes of intersections.
Dong Xuan (Dong Son) intersection completed and put into use, creating favorable conditions for people to travel.
On the route of the Mai Son - National Highway 45 expressway project through Thanh Hoa province, there are Gia Mieu intersection (Km 295+800), Ha Linh intersection (Km 306+000), Thieu Giang intersection (Km 315+380), Dong Xuan intersection (Km 327+142), Dong Thang intersection (Km335+400).
Lighthouse
Source
Comment (0)