Up to now, Nhon Trach 3 and Nhon Trach 4 Power Plant Project in Dong Nai has completed 99.8% of the total work volume. Equipment procurement and installation work has been completed.

Báo Đồng NaiBáo Đồng Nai11/07/2025

Of which, Nhon Trach 3 Plant has been connected to the national grid since February 5, 2025 and is in the acceptance testing phase, expected to be commercially operational in mid-August 2025.

Nhon Trach 4 Plant will connect to the grid for the first time on June 26, 2025. According to the plan, after completing the testing and technical evaluation steps, the plant will officially go into commercial operation in November 2025.

Nhon Trach 3 and Nhon Trach 4 Power Plants are key national projects in the energy sector in the province. The project has a total investment of about 1.4 billion USD, a capacity of 1.5-1.6 thousand MW, and is the first energy project using imported liquefied natural gas (LNG) to generate electricity in Vietnam. When operating, the plants not only contribute to increasing the power supply for the national system, but also aim at the goal of sustainable energy transition, reducing greenhouse gas emissions and developing a green economy .

Ban Mai

Source: https://baodongnai.com.vn/kinh-te/202507/nha-may-dien-nhon-trach-3-va-nhon-trach-4-hoan-thanh-998-khoi-luong-tong-the-e3515cc/


Comment (0)

No data
No data

Same tag

Same category

There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;