The first meters of tunnel on Khanh Hoa highway

Báo Giao thôngBáo Giao thông19/06/2024


The Khanh Hoa - Buon Ma Thuot Expressway Construction Project Phase 1 has a total investment of VND 21,935 billion. The total length of the project is about 116.577km, officially started construction on June 18, 2023 and is expected to be completed in 2027.

The project is divided into 3 components. Of which, component project 1 is invested by Khanh Hoa Provincial People's Committee, component project 2 is invested by the Ministry of Transport and component project 3 is implemented by Dak Lak Provincial People's Committee.



Source: https://www.baogiaothong.vn/nhung-met-ham-dau-tien-tren-cao-toc-khanh-hoa-buon-ma-thuot-192240619153851295.htm

Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;