Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep inspected the progress of upgrading National Highway 28B.

On September 10, Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep led the provincial working delegation to inspect the progress of site clearance and construction of the project to renovate and upgrade National Highway 28B.

Báo Lâm ĐồngBáo Lâm Đồng10/09/2025

The delegation surveyed the entire route from the intersection of National Highway 28B with National Highway 20, Ta Hine commune to Luong Son commune and worked with local authorities and related units.

dsc01294.jpg
Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep discussed and directed many contents related to construction items with the contractor.

According to the report of the Department of Construction, by September 8, 2025, the project had cleared 94% of the area, equivalent to 64.4/68.49 hectares. The site along the construction route has been handed over to the investor for 62km/68km (reaching 91.1%), with 6km remaining. At the construction site, contractors have deployed 41/68km of crushed stone aggregate and 33/68km of dense asphalt concrete.

However, the construction progress is still slow compared to the requirements. The work of relocating technical infrastructure still has many backlogs, only 7,676/12,021m of water supply pipes and 30/81 medium voltage power positions, 3 low voltage poles, 42 residential power poles have been completed... Meanwhile, some sections of the route have the ground but have not been constructed in time.

dsc01326.jpg
A section of the bridge under construction

Localities where the project passes through said that the biggest difficulty at present is the slow payment of compensation, and some households have not agreed to hand over the land. In addition, the determination of land boundaries related to the Dai Ninh Hydropower Project has not been completely resolved, causing difficulties in compiling compensation records.

Commune authorities also reported that the coordination between the construction unit and the locality was not close. The construction plan was unclear, leading to difficulties in propaganda, mobilizing people and supporting the implementation of site clearance.

dsc01212.jpg
Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep assessed that compared to last month, the project had some positive changes but did not meet requirements.

Speaking at the meeting, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep assessed that compared to last month, the project had some positive changes but had not yet met the requirements. The Vice Chairman of the Provincial People's Committee pointed out that the progress of implementing the items was "extremely slow". There was a lack of vehicles and human resources, and contractors had not yet organized synchronous construction along the entire route.

dsc01489.jpg
Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep delivered a concluding speech at the working session.

Regarding site clearance work, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep requested that this is the main responsibility of the local authorities where the project passes through, but there must be close coordination between the investor, consulting and supervising units.

The land price appraisal and approval has been completed, units must urgently develop compensation plans in September. Payments must be made to people by October 30, 2025 at the latest, of which at least 30-40% of households must receive money before October 15.

Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep

For investors and contractors, the Vice Chairman of the Provincial People's Committee requested to immediately overcome the limitations. Organize construction right on the handed-over area, work neatly as you go, quickly complete the constructed sections to put them into operation, not to affect people's lives.

The Vice Chairman of the Provincial People's Committee directed to review the progress of each contractor, assign responsibility for the quality and safety of the project. At the same time, arrange traffic controllers at the construction sections to ensure safety.

Source: https://baolamdong.vn/pho-chu-tich-ubnd-tinh-vo-ngoc-hiep-kiem-tra-tien-do-nang-cap-quoc-lo-28b-390784.html


Comment (0)

No data
No data

Same tag

Same category

Admiring Gia Lai coastal wind power fields hidden in the clouds
Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;