Railway route through Yen Bai opens from 9pm tonight (October 8)

Báo Giao thôngBáo Giao thông08/10/2023


According to information from Vietnam Railways Corporation, at around 9:00 p.m. tonight (October 8), the landslide in Yen Bai was repaired after nearly two days of urgent repair, preparing to open the entire Yen Vien - Lao Cai route.

Previously, due to prolonged heavy rain in Yen Bai province on October 6, by the morning of October 7, some infrastructure locations were damaged, making it impossible for trains to run.

Đường sắt Lào Cai qua Yên Bái đã khắc phục xong, thông đường toàn tuyến - Ảnh 1.

The railway concentrated human resources to rescue throughout the night at the severe landslide point at Km 180+090 - Km 180+125 of Yen Vien - Lao Cai route, in Yen Thai commune, Van Yen district, Yen Bai province.

Specifically, at the Ngoi Hop - Mau A section of the Yen Vien - Lao Cai railway, some points had roadbeds washed away, roadbed slopes collapsed, soil and rocks filled ditches and overflowed onto the roadway; Landslides in cable trenches damaged underground signal cables. The railway had to block off the section to organize rescue and remedy the consequences.

Preliminary damage to the road and bridge: Km 178+200 - Km 178+260 had a landslide on the right side of the railway route, had to ban trains at 6:30 this morning (October 7); Km 179+150 - Km 179+200 had a landslide on the right side of the railway route, soil covered the rail surface, had to ban trains from 4:15 this morning. In particular, Km 180+090 - Km 180+125 had the entire roadbed collapsed, the sleepers were hanging at an average depth of 6m, had to ban trains at 2:10 this morning.

Đường sắt Lào Cai qua Yên Bái đã khắc phục xong, thông đường toàn tuyến - Ảnh 2.

On October 8, the railway force continued to repair the railway in the landslide area.

Particularly, Km 182+700 - Km 182+750 had a landslide on the right side of the railway track, banned trains at 2:45 this morning for repair and the speed limit was restored to 5km/h at 6:50 (with staff guiding); Km 183+740 - Km 183+780 had a landslide on the right side of the railway track, soil covered the rail surface, banned trains from 3:24 this morning for repair and the speed limit was restored at 4:25.

Regarding transportation, to ensure safety for passengers and goods, Vietnam Railways Corporation has proactively stopped trains at stations along the route and banned trains from passing through this area.

Immediately after receiving the news of landslides and damage to railway infrastructure, local railway units mobilized hundreds of personnel and machinery for continuous repair. By 9:00 p.m. tonight, the repair was completed, returning the track to a speed of 5km/h with a guide for trains through Km 179+950 - Km 180+250. After the construction train safely arrives at Mau A station, the section will be cleared for train H2205 to run to Ngoi Hop station, officially opening the route.



Source: https://www.baogiaothong.vn/thong-tuyen-duong-sat-qua-yen-bai-tu-21h-toi-nay-8-10-192231008214800657.htm

Comment (0)

No data
No data

Same tag

Same category

Admiring Gia Lai coastal wind power fields hidden in the clouds
Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;