Rach Mieu 2 Bridge is nearly 6 months ahead of schedule, to be completed by the end of 2025

On July 12, Minister of Construction Tran Hong Minh and his delegation inspected the Rach Mieu 2 Bridge Project - a key traffic project connecting Dong Thap and Vinh Long provinces.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng12/07/2025

Minister of Construction Tran Hong Minh inspects the Rach Mieu 2 bridge project. Photo: MT
Minister of Construction Tran Hong Minh inspects the Rach Mieu 2 bridge project. Photo: MT

Reporting to the working group, Mr. Tran Van Thi, Director of My Thuan Project Management Board (Ministry of Construction) said that up to now, the project has completed more than 96.5% of the work volume. It is expected that the entire project will be completed by the end of 2025, nearly 6 months ahead of schedule compared to the original plan.

At the construction site, there are currently about 600 engineers and workers divided into 30 construction teams, focusing on implementing the final items such as: installing median strips, painting road markings, installing lighting systems and constructing asphalt concrete layers for the remaining sections on the Dong Thap bank.

CAU RM2.jpg
Minister of Construction Tran Hong Minh inspects the Rach Mieu 2 bridge project. Photo: MT

Speaking at the inspection, Minister Tran Hong Minh praised the urgent and responsible working spirit of the staff, engineers and workers at the construction site. The Minister assessed that not only was the Rach Mieu 2 Bridge ahead of schedule by nearly half a year, it was also a testament to the significant progress in the construction industry's autonomy, as domestic units took control of the entire design, construction and equipment manufacturing process - contributing to cost savings and improving investment efficiency.

“This is a remarkable achievement. Collectives and individuals with good achievements should be commended and recommended for rewards. Effective contractors should also be given priority to participate in the next projects,” the Minister emphasized.

z6796645946703_39a1f698ae910236bf3fe5be2df395a4.jpg
Rach Mieu 2 Bridge is an important traffic project in the Mekong Delta region. Photo: MT

The Rach Mieu 2 Bridge Project has a total investment of more than 6,810 billion VND from the State budget. The bridge starts at Dong Tam intersection (National Highway 1 intersects with Provincial Road 870, Dong Thap province) and ends at Km16+660 on National Highway 60 (in Vinh Long province), about 0.71km from Ham Luong Bridge.

The main bridge is designed in a modern cable-stayed form, 1.971km long, 21.5m wide with 4 lanes for motor vehicles, designed speed of 80km/h. When completed, Rach Mieu 2 Bridge will contribute to reducing the load on the existing Rach Mieu Bridge, relieving traffic pressure, and at the same time creating a driving force for socio-economic development in the Mekong Delta region.

Source: https://www.sggp.org.vn/cau-rach-mieu-2-vuot-tien-do-gan-6-thang-ve-dich-vao-cuoi-nam-2025-post803491.html


Comment (0)

No data
No data

Same tag

Same category

Lost in cloud hunting in Ta Xua
Admiring Gia Lai coastal wind power fields hidden in the clouds
Coffee shops in Hanoi are bustling with Mid-Autumn Festival decorations, attracting many young people to experience
Vietnam's 'sea turtle capital' recognized internationally

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product