Vietnam.vn - Nền tảng quảng bá Việt Nam

Road construction project to Hanoi University: Need to speed up progress to avoid waste

The project to build a road to Hanoi University was started in December 2023 with a total length of 560.31m, construction time of 540 days. However, up to now, the construction deadline has passed, the project has only completed about 55% of the volume according to the approved design documents.

Hà Nội MớiHà Nội Mới05/09/2025

Project delays not only waste investment resources but also cause difficulties for people's travel, making the urban area look shabby and the environment polluted.

Slow progress due to site clearance problems

The project to build a road to Hanoi University is invested by the People's Committee of Nam Tu Liem District (old), now the People's Committee of Dai Mo Ward. The project is implemented to concretize the H2-2 Planning, scale 1/2000, approved by the Hanoi People's Committee in Decision No. 6631/QD-UBND dated December 2, 2015.

img_8677.jpg
Due to problems with site clearance, the project has had to stop construction for many months, causing a waste of investment budget. Photo: TH

Accordingly, the project has an investment of over 127.3 billion VND, designed with a total length of 560.31m, divided into three sections: Route 1 is 108.75m long, the roadbed width is 23.5m, connecting from Nguyen Trai Street to the gate of Hanoi University; Route 2 is 309.94m long, the roadbed width is 17.5m, connecting from the gate of Hanoi University to Phung Khoang Street; Route 3 is 141.62m long, the roadbed width is 23.5m, connecting from Route 2 to Nguyen Trai Street. All of the above sections are designed with a synchronous system of roads, trees, lighting, water supply, drainage, electricity supply, technical trenches, telecommunication cables, fire prevention and fighting... according to the approved planning.

After starting construction, the investor directed the construction unit to implement the project in accordance with regulations, but due to problems with site clearance, construction had to be slowed down, then stopped completely from the end of 2024 until now.

Officer of the Economic , Infrastructure and Urban Department of Dai Mo Ward, Duong Quang Khai, said that the total area cleared for the project is 12,097.7m2 , including 1,187.1m2 of residential land of 51 households; 611.3m2 of non- agricultural land of 5 organizations and 10,299.3m2 of land managed by the People's Committee of Dai Mo Ward.

"Up to now, the locality has temporarily handed over 9,997.7 square meters of land, reaching 90% of the total cleared area to the construction unit to implement the project. Currently, there is still a part of the land area of ​​households and the temple's incense land that has not been cleared yet. In addition, the relocation of underground and above-ground works is still being implemented, which is also the reason affecting the project's progress," Mr. Duong Quang Khai explained.

img_8680.jpg
Many households have occupied land in the project area to set up umbrellas and tents to sell goods, causing a mess; and have discharged water and garbage, polluting the environment.

Propaganda and mobilization of people to hand over the site soon

According to a survey by a reporter from the Hanoi Moi Newspaper, the project to build a road to Hanoi University is unfinished, only completing about 55% of the designed volume, making this area messy and seriously polluted. Along route 2 of the project, the section connecting from the gate of Hanoi University to Phung Khoang Street (next to the back gate of Phung Khoang Market), has long been turned into a "flea market", with many people setting up umbrellas and tents to sell agricultural products and food in the morning.

Garbage and wastewater are dumped directly onto the street by traders without being cleaned up, causing the air in this area to always smell unpleasant and the wastewater to stagnate and turn black. Here, sewers, concrete slabs, etc. used for construction are scattered on both sides of the road, making it difficult for people to move around.

Mr. Tran Quoc H., who lives near Phung Khoang market, Dai Mo ward, said that the slow and prolonged construction of the project has made the area around the project messy. In particular, because the drainage system is still under construction, every time it rains, the entire project area is flooded, causing traffic safety problems.

"I request the investor to speed up the project implementation progress and complete it soon so that people can travel less arduously," Mr. H. expressed.

img_8683.jpg
Local residents hope the project will soon be implemented, completed, and put into use. Photo: TH.

According to the staff of the Economic, Infrastructure and Urban Department of Dai Mo Ward, Duong Quang Khai, in order to speed up the project implementation progress, the Ward People's Committee is directing functional branches, residential groups, and organizations to mobilize and propagate so that households with remaining residential land area agree with the compensation, support and resettlement plan, and hand over the site soon. After having a clean site, the investor will direct the contractor to speed up the construction progress of the remaining items such as roadbed, drainage, technical trenches, sidewalks, tree planting..., striving to complete the project soon to put it into use.

The project's delay not only causes waste, but also makes it difficult for people in the area to travel. We propose that the People's Committee of Dai Mo Ward focus on clearing the remaining land, speeding up the progress, putting the project into use soon, meeting people's expectations, contributing to the completion of the infrastructure system and landscape in the area in particular and Dai Mo Ward in general.

Source: https://hanoimoi.vn/du-an-xay-dung-duong-vao-truong-dai-hoc-ha-noi-can-day-nhanh-tien-do-tranh-lang-phi-715202.html


Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;