The 500 kV Line 3 project from Quang Trach ( Quang Binh ) to Pho Noi (Hung Yen) is entering a critical phase with time being counted by the day. Sticking closely to the project's schedule, regardless of the sun or rain, the technical team regularly works on hundreds of meters high electric poles and hangs in mid-air to perform especially difficult operations when erecting poles and pulling wires.

The

According to the representative of the National Power Transmission Corporation, the 500 kV Line 3 Project from Quang Trach (Quang Binh) to Pho Noi ( Hung Yen ) always has about 8,000-10,000 officers, engineers, workers, and laborers working at the construction site.

The

Installing the line positioning frame is the final step to complete the wire-pulled anchorages.

The

Suspended in the air, the "spider men" are working hard in harsh weather conditions in Thanh Hoa without any means of protection.

The

Contractor workers of Phuong Hanh Company Limited check the final items at column 76 in Nga Giap commune (Nga Son).

The

On hot days, workers often start work from 5:30 am and take turns every 2-3 hours to ensure their health.

The

The wire pulling construction teams are professional forces, mobilized from many provinces to Thanh Hoa.

The

Technical workers of the National Power Transmission Corporation increased manpower to install power lines for contractors.

The

Special pose of "spider-man" installing insulators in package 11 through Dai Loc commune (Hau Loc).

The

Despite working at high intensity and in harsh weather conditions, technical workers are all very optimistic because they are honored to contribute to a key project of the whole country.

The

Workers of Phuong Hanh Company Ltd. planted the national flag on the completed power line section passing through Nga Giap (Nga Son).

The 500 kV line 3 in Thanh Hoa province is 131 km long, passing through 11 districts and towns in the province, including 299 pole foundation positions and 137 anchorages. Currently, 243 steel poles have been erected on the line in Thanh Hoa province; 15 anchorages have been completed and 18 anchorages are being erected.

Lighthouse - Tung Lam


Source

Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;