On September 26, the Government issued Resolution No. 297/NQ-CP on implementing Resolution No. 220/2025/QH15 of the National Assembly on investment policy for the Ho Chi Minh City Ring Road 4 construction investment project.
Ho Chi Minh City, Dong Nai and Tay Ninh provinces can apply the form of designated bidding.
For the group of component projects invested in the form of public investment, according to Resolution 297, the Chairman of the People's Committee of Ho Chi Minh City and the Chairman of the People's Committees of Dong Nai and Tay Ninh provinces exercise the authority of the investment decision maker, organize the preparation and appraisal of the Feasibility Study Report and decide to approve the project.
The component project group is implemented under the public-private partnership method. The People's Committee of Ho Chi Minh City and the People's Committees of Dong Nai and Tay Ninh provinces organize the appraisal and approval of component projects under the public-private partnership method.
The Resolution clearly states that the Chairman of the People's Committee of Ho Chi Minh City and the Chairmen of the People's Committees of Dong Nai and Tay Ninh provinces and the heads of competent agencies shall apply the form of designated bidding in the process of implementing the Project for consulting, non-consulting, consulting packages for planning adjustment and construction of infrastructure for resettlement areas.
The Resolution also allows the People's Committee of Ho Chi Minh City and the People's Committees of Dong Nai and Tay Ninh provinces to simultaneously carry out a number of tasks related to land recovery, compensation, support, resettlement and identification of construction solid waste dumping sites during the project preparation phase.
Specifically, organize the preparation, approval, and handover of site clearance design documents for component projects in each phase; organize the review, approval, and adjustment of land use planning and plans;
Based on the approved site clearance design documents, localities will preliminarily determine resettlement needs, review land funds and resettlement housing funds to determine locations and forms of resettlement; organize planning and investment projects to build resettlement areas...
In addition, the Resolution allows simultaneous implementation of procedures to shorten the time for performing the following tasks: appraisal, decision to approve appraisal results of environmental impact assessment reports; local adjustment of planning related to the Project to ensure the progress of implementing component projects.

Strive to complete the Project by 2028
In addition, the Resolution assigns the Ho Chi Minh City People's Committee as the focal agency to organize the implementation of the Project; preside over the synthesis and submission to competent authorities for consideration and decision on adjusting the Project's investment policy (if any).
Preside over the preparation of Government Reports and Submissions to the Ministry of Construction for synthesis and submission to competent authorities on the Project implementation status and preside over and coordinate with localities to organize the development of progress and detailed plans for Project implementation.
Preside over the synthesis and coordination with the People's Committees of Dong Nai and Tay Ninh provinces to carry out investment supervision and evaluation work according to the provisions of law.
Next, based on the specific situation and conditions, preside over the establishment of a Working Group to implement the Project immediately after the issuance of this Resolution.
The People's Committee of Tay Ninh province was assigned to propose a medium-term public investment plan using central budget capital for the Project in the 2026 - 2030 period for component projects, and send it to the Ministry of Finance for synthesis and reporting to competent authorities.
Report to the Government for consideration of the decision to adjust to the form of public investment in case the component project with the Provincial People's Committee as the competent authority cannot select an investor.
The Resolution clearly states: The People's Committee of Ho Chi Minh City and the People's Committee of Dong Nai province shall report to the People's Council of the same level to decide to adjust to the form of public investment in case the component project cannot select an investor.
In addition, the People's Committee of Ho Chi Minh City and the People's Committees of Dong Nai and Tay Ninh provinces are responsible for the progress, quality and efficiency of the projects under their management; absolutely not allowing negativity and waste to occur, causing loss of state assets.
The Resolution emphasized that the People's Committees of the above provinces and cities strive to complete the Project in 2028 and put it into operation in 2029.
In particular, for the group of investment components in the form of public investment, the organization is required to establish, examine, appraise, decide to approve the project, complete before December 31, 2025 and carry out the next work to start construction before June 30, 2026.
For component project groups implemented under the public-private partnership method, the organization shall prepare, examine, appraise, decide on approval of component projects and select investors to be completed before June 30, 2026; carry out the following tasks to start construction in the fourth quarter of 2026.
The total length of the entire Ho Chi Minh City Ring Road 4 is about 207.26 km, starting at the Toc Tien - Chau Pha intersection (intersection area with Bien Hoa - Vung Tau expressway and provincial road DT.992), ending at the intersection with the North - South axis road at Hiep Phuoc Port area, Nha Be district, Ho Chi Minh City.
The total investment length is about 159.31 km; including: the section through Ba Ria - Vung Tau province (old) is about 18.23 km long; the section through Dong Nai province is about 46.08 km long. The section through Ho Chi Minh City is about 20.5 km long and the section through Long An province (now Tay Ninh) is about 74.5 km long.
Preliminary total investment of the project is about 120,413 billion VND.