Review the entire Vinh Hao - Phan Thiet expressway project

On October 10, the Government Office issued a document conveying the direction of Deputy Prime Minister Tran Hong Ha on handling the erosion situation on the Vinh Hao - Phan Thiet expressway.

Báo Lâm ĐồngBáo Lâm Đồng11/10/2025

z7104077246927_4dd37431776fa1c1e09be4a295bcc8a9.jpg
Vinh Hao - Phan Thiet Expressway

The Deputy Prime Minister requested the Ministry of Construction to urgently direct relevant agencies and units to review the entire project, promptly detect and thoroughly handle damaged locations and damage risks, ensuring the quality and safety of the project and traffic safety on the Vinh Hao - Phan Thiet expressway in accordance with the authority and provisions of law.

Vinh Hao - Phan Thiet Expressway section passing through the location of sand overflow and water stagnation
Vinh Hao - Phan Thiet Expressway section passing through the location of sand overflow and water stagnation

The Deputy Prime Minister also assigned the Ministry of Construction to inspect and assess the landslide and flooding situation at key national traffic projects, clarify the causes and responsibilities, and implement remedial solutions.

Vinh Hao - Phan Thiet Expressway is more than 100 km long, passing through Lam Dong province. This expressway has a total investment of over 10,850 billion VND, opening to traffic from May 2023. This is a section of the North - South expressway, the route has 4 lanes, maximum speed of 90 km/h.

Vehicles were mobilized to the sand spill location to fix the problem.
Vehicles were mobilized to fix the sand spill incident.

In September 2025, on this highway, there were consecutive incidents that posed a risk to traffic safety. Notably, after a heavy rain, the Vinh Hao - Phan Thiet highway section Km213 through Ham Liem commune had erosion locations creating frog-shaped edges of the roadbed. The eroded part of the roadbed formed gullies. Some eroded sections penetrated deep into the roadbed, forming landslides, posing a potential danger to vehicles.

z7104007351242_e027caa97106f6f360004e52a73d86c0.jpg
Section Km213 through Ham Liem commune has erosion locations creating frog-jaws on the edge of the foundation.

In addition, heavy rain also caused sand and soil to overflow onto the highway surface, causing water to stagnate in the section passing through Ham Liem commune (Lam Dong), about 7 km from Ma Lam intersection on National Highway 28.

After the sand spill incident, relevant units mobilized human resources and vehicles to the scene to clean up the sand and clear the stagnant water. To prevent the erosion from creating a frog-shaped edge of the foundation, the management and maintenance unit of the Vinh Hao - Phan Thiet expressway section temporarily reinforced it by stacking sandbags on top of each other.

z7104007475865_3b53bd81f01ab12a38345c704edef789.jpg
Erosion creates a frog jaw on the edge of the highway foundation

Project Management Board 7 (Ministry of Construction) said that the cause of the landslide and the exposed edge of the Vinh Hao - Phan Thiet expressway was due to the removal of the curb to drain water on the road surface...

Source: https://baolamdong.vn/ra-soat-toan-bo-du-an-cao-toc-vinh-hao-phan-thiet-395428.html


Comment (0)

No data
No data

Same tag

Same category

Visit U Minh Ha to experience green tourism in Muoi Ngot and Song Trem
Vietnam team promoted to FIFA rank after victory over Nepal, Indonesia in danger
71 years after liberation, Hanoi retains its heritage beauty in the modern flow
71st anniversary of Capital Liberation Day - stirring up the spirit for Hanoi to step firmly into the new era

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product