According to old farmer Nguyen Thanh L. (area 3), this area used to have a regulating lake near Quy Nhon 3 spillway, adjacent to Thi Nai lagoon, ensuring flood drainage and preventing salinity for hundreds of hectares of rice. However, recently, the construction company of the new urban area project has filled the drainage system with soil, causing prolonged flooding of the fields.
“Never before have the fields been flooded like this in the middle of a hot season. For the past few months, farmers here have been very upset and worried because their fields are gradually shrinking, shrinking and becoming abandoned,” said old farmer Nguyen Thanh L. (in area 3) worriedly.
According to Mr. Nguyen Thanh L., in the past, to ensure the production of hundreds of hectares of rice fields here, it was necessary to maintain a reservoir to regulate, drain floods and prevent salinity in the area near Quy Nhon 3 spillway, adjacent to Thi Nai lagoon. However, recently, the government allowed a company to fill in the new urban area. During the construction process, the company also filled in the flood drainage system, causing the fields to be flooded and damaged.
>>>Short clip about the incident and people's feedback and opinions:

According to Mr. Nguyen Thanh L., in the past, to ensure the production of hundreds of hectares of rice fields here, it was necessary to maintain a reservoir to regulate, drain floods and prevent salinity in the area near Quy Nhon 3 spillway, adjacent to Thi Nai lagoon. However, recently, the government allowed a company to fill in the new urban area. During the construction process, the company also filled in the flood drainage system, causing the fields to be flooded and damaged.

The heaviest damage was in area 5, with about 62 hectares of rice belonging to nearly 100 households affected. “Many households had to sow and transplant rice 3-4 times, wasting effort and money; some households had to pump water for 25 days to save the rice,” said Mr. Ng. H., owner of 6 sao of rice here.
Mr. Do Xuan Sanh, an irrigation officer of Nhon Binh I Agricultural Cooperative, informed: "In this year's Summer-Autumn crop alone, more than 15/62 hectares of rice in area 5 were forced to abandon due to flooding. People were very upset, they signed a collective petition asking me to represent them to send it to all levels and sectors, requesting early investment in a new flood drainage system so that they can feel secure in production and need compensation and support for damages."

According to the residents' feedback, the Provincial People's Committee previously planned and granted land for the enterprise to build an urban area that overlapped with their flood drainage, anti-inundation, and saltwater intrusion prevention systems. Therefore, the enterprise's implementation was not wrong, but the shortcomings and inadequacies lay with the government.
Speaking to SGGP reporters, a leader of the Department of Agriculture and Environment of Gia Lai province confirmed that the flooded area belongs to the Cho Goc new urban area project (CG-01) invested by Phu Gia Riverside Company Limited. Previously, the leaders of the People's Committee of Binh Dinh province (now Gia Lai province) had a meeting, listened to the opinions of all parties and had conclusions and specific instructions.
Vice Chairman of the Provincial People's Committee Nguyen Tuan Thanh concluded: When there was no drainage solution, the enterprise filled up the 5-compartment bridge (through National Highway 19), leveled the ground for construction of the project, blocking the flood drainage and draining the current situation, causing about 60 hectares of rice fields of people in area 5 to be flooded...

Thereby, the leaders of the Provincial People's Committee directed the Department of Agriculture and Environment to be the investor, organize the preparation of technical economic reports, appraisal, approval and implementation of construction of the new canal, lowering the elevation of the new public service road south of National Highway 19 (section from Ha Thanh 6 bridge to Dien Bien Phu street).
Phu Gia Riverside Company Limited is responsible for arranging funds to carry out compensation, site clearance and investment in the above canal to restore the flood drainage canal, serving production and daily life of the people...

The new urban area project CG‑011 was established in 2019, with an initial capital of over VND 1,777 billion (direct investment capital of the investor). On July 6, 2020, the Provincial People's Committee approved the detailed planning at a scale of 1/500, an area of over 62 hectares, a population of 9,100 people; planning for land use for civil, service, urban, resettlement...