On the afternoon of December 27, at the construction site of Tan Son Nhat T3 terminal, the urgent working atmosphere was evident in every position. The project is currently in the "sprint" phase to reach the finish line before April 30, 2025.
Currently, at the Tan Son Nhat T3 terminal construction site, there are more than 2,500 workers and engineers, hundreds of machines and equipment working day and night - Photo: CHAU TUAN
The Airports Corporation of Vietnam (ACV) said Tan Son Nhat is one of the three most important and largest airports in the country. The construction of Terminal T3 with a capacity of 20 million passengers per year will "share the burden" of the currently overloaded Terminal T1, improving the quality of service for the people.
Currently, the T3 terminal construction project has completed the concrete and rough architecture. Of which, the 7,500-ton steel roof structure and 45,000m2 aluminum roof have reached 100%. The glass wall part has reached 94%, expected to be completed in December 2024.
At the same time, many other items of T3 terminal have been and are being completed. Up to now, the total volume has reached about 83%, striving to complete the whole by April 30, 2025 for operation and exploitation.
Mr. Le Khac Hong - head of Tan Son Nhat T3 terminal project management board - said the project has achieved good results in many aspects of construction progress and quality, as well as labor safety.
"To inaugurate the project on April 30, 2025, we must complete the project one month earlier, meaning there are only 90 days left to complete the project. This is a huge challenge, requiring relevant units to be more united, to try harder and to be more determined.
Therefore, the construction site management board needs to pay special attention and promptly resolve any problems that arise during construction, creating the most favorable conditions for contractors.
"We will mobilize all resources to the maximum, find solutions to ensure the completion of equipment installation, safe and quality operation and acceptance, and ensure the completion of the project and its commissioning," said Mr. Hong.
Current image of Tan Son Nhat T3 terminal:
The T3 terminal construction project includes four main items: a passenger terminal, a high-rise parking lot combined with non-aviation services, a flyover system in front of the terminal and an aircraft parking lot with a total investment of VND10,990 billion - Photo: CHAU TUAN
The glass wall of terminal T3 has reached 94% - Photo: CHAU TUAN
The construction unit is also speeding up the progress of many other items - Photo: CHAU TUAN
To speed up construction progress, contractors have applied the method of dividing construction work into small sections, combining iron structure processing at the factory - Photo: CHAU TUAN
Inside the passenger terminal, there is currently a massive scaffolding system to help workers work safely at height - Photo: CHAU TUAN
The 7,500-ton steel roof structure has been completed - Photo: CHAU TUAN
Outside the passenger terminal, bridges and overpasses are also being built - Photo: CHAU TUAN
The investor said that to ensure progress, the company requires contractors to follow the Government 's spirit of "fighting the sun and rain, eating and sleeping quickly, working in 3 shifts, working through holidays and Tet" - Photo: CHAU TUAN
Terminal T3 is the largest domestic passenger terminal in the country, with a capacity of 20 million passengers per year, and an investment of nearly VND11,000 billion from the capital of the Airports Corporation of Vietnam (ACV) - Photo: CHAU TUAN
Launching emulation to soon bring T3 terminal to the finish line
On the same afternoon, Vietnam Airports Corporation (ACV) held a preliminary ceremony to summarize the 90-day and night competition to complete the entire terminal roof, facade and power the project, launching a 120-day and night competition to finish before April 30, 2025.
On behalf of the investor, Mr. Le Khac Hong praised the efforts of the contractors who responded to the competition, accelerated the construction progress, and soon completed the project ahead of schedule.
Source: https://tuoitre.vn/can-canh-dai-cong-truong-nha-ga-t3-tan-son-nhat-dang-chay-nuoc-rut-de-ve-dich-20241227203731435.htm