Chi Linh and Hai Duong City achieved progress in the province's 2-month public investment disbursement scenario.

Việt NamViệt Nam01/03/2025


investment capital solution
The project to renovate and upgrade provincial road 395 and the road leading from Cay bridge to provincial road 394 in Binh Giang district, invested by the district's Construction Investment Project Management Board, is speeding up construction progress.

According to the update on the progress of public investment disbursement on the software for monitoring the plan and progress of public investment of Hai Duong province, by February 28, the province had disbursed more than 523 billion VND of public investment capital, reaching 5.5% of the plan assigned by the province, 5% of the plan assigned by the Prime Minister, equivalent to the same period in 2024.

Thus, compared with the province's public investment disbursement plan scenario for 2025, Hai Duong has not yet ensured the plan (the cumulative plan for the first two months of the year reached 8%).

Chi Linh City is the locality with the highest rate of public investment disbursement, reaching 8.6%; Hai Duong City is second, reaching 8.4%, followed by Thanh Ha with 7.8%. Some units and localities do not have disbursement data such as the Provincial Police, the Provincial Party Committee Office, and Cam Giang District. Some localities have disbursement data but the rate is low such as: Thanh Mien District reaching 0.2% of the plan; Kim Thanh reaching 0.9% of the plan, Binh Giang reaching 1%...

The disbursement of public investment capital has not met the planned scenario due to the slow progress in compensation and site clearance support for project construction, and the slow handover of site by many projects. Determining the origin of land of households has encountered many difficulties due to multiple transfers, which takes time.

The supply of some raw materials such as soil, sand, etc. is limited. The prices of many raw materials have increased compared to the time of bidding, increasing the project cost.

Previously, according to information from the Ministry of Finance , in the first two months of the year, the country's estimated disbursement of public investment capital reached 60,423.8 billion VND, reaching 6.9% of the plan, reaching 7.32% of the plan assigned by the Prime Minister.

HV


Source: https://baohaiduong.vn/chi-linh-va-tp-hai-duong-dat-tien-do-kich-ban-giai-ngan-von-dau-tu-cong-2-thang-cua-tinh-406314.html

Comment (0)

No data
No data

Same tag

Same category

Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory
Tò he – from a childhood gift to a million-dollar work of art

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;