Vietnam.vn - Nền tảng quảng bá Việt Nam

Speeding up the construction progress of the Northern Mountainous Region General Hospital project in Quang Nam

Việt NamViệt Nam24/03/2024

ps-teachers-are-sorry-for-students.00_33_22_07.still011.jpg
A corner of the Department of Infectious Diseases - Tuberculosis with the connecting house. Photo: LAN NHI

The Department of Infectious Diseases - Tuberculosis (5 floors, construction area of ​​935.8m2 and total floor area of ​​4,899m2 ), mortuary (1 floor, construction area of ​​73.8m2 ), connecting house, auxiliary items and equipment of the Project to invest in the construction of the Northern Mountainous Region General Hospital of Quang Nam started on October 20, 2023, expected to be completed after 450 days with a construction value of more than 41 billion VND.

The project is invested by the Department of Health ; the construction contractor includes a consortium of Saiko Construction and Trading Company Limited, Huy Nhu Company Limited and HTG Mechanical, Electrical and Fire Prevention and Fighting Company Limited.

ps-teachers-are-sorry-for-students.00_33_38_22.still012.jpg
Supervision and construction units actively speed up the project progress. Photo: LAN NHI

Up to now, the Department of Infectious Diseases - Tuberculosis has completed the foundation, poured concrete floors for floors and roof floors, built walls for floors 1, 2, 3; the main house has completed pouring concrete floors, plastering walls, waterproofing. The connecting corridor has completed the foundation stage, poured concrete floors for roof floors for more than 40m in 112m length.

Mr. Pham Thanh Tung - Director of Saiko Construction and Trading Company Limited said that up to now, the construction volume of the rough parts of the items is more than 85%; the joint venture contractor is focusing on speeding up the construction progress. If the investor ensures the capital, the project will be completed and handed over on September 2 this year, 4 months ahead of the contract.


Source

Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;