- On the afternoon of September 29, the Provincial Steering Committee for National Target Programs (CTMTQG) held a conference to evaluate and accelerate the implementation of the CTMTQG for socio -economic development in ethnic minority and mountainous areas. The conference was held directly at the Provincial People's Committee headquarters and connected online to the People's Committees of communes and wards in the province. Comrade Doan Thanh Son, Vice Chairman of the Provincial People's Committee, Deputy Head of the Provincial Steering Committee for National Target Programs attended and directed the conference.
According to the report of the Department of Ethnic Minorities and Religions, the total capital used (including extended capital and capital allocated in 2025) for the program is over 1,747 billion VND. The result of capital disbursement from the beginning of 2025 to August 31, 2025 is 349.8 billion VND, reaching 20.03% of the total capital used in 2025. Of which, development investment capital has been disbursed 232.9 billion VND, reaching 29.6%; public service capital has been disbursed 116.9 billion VND, reaching 12.18%.
Projects with relatively good disbursement rates include: Project 4: Investing in essential infrastructure to serve production and life in ethnic minority and mountainous areas and public service units in the ethnic sector; Project 5: Developing education and training to improve the quality of human resources; Project 6: Preserving and promoting the fine traditional cultural values of ethnic minorities associated with tourism development...
In general, the implementation of disbursement of capital sources under the program still faces many difficulties and obstacles due to a number of reasons such as: the project no longer has an implementation target; some projects have problems related to site clearance and environmental procedures; the contractor selection work must be redone, the project approval process is still slow...
At the conference, delegates focused on discussing and clarifying the results achieved, the shortcomings and limitations in implementing the program and proposed and recommended solutions to effectively implement the program in the coming time.
Concluding the conference, the Vice Chairman of the Provincial People's Committee requested the People's Committees of communes and wards to urgently review and complete investment procedures and construction of projects invested by the communes; coordinate with relevant departments and branches to speed up the progress of project implementation.
Departments and branches regularly monitor, urge and guide units to implement the contents chaired and monitored by the department and branch. For recommendations from communes and wards, departments and branches synthesize and send to the Department of Ethnic Minorities and Religions no later than October 2.
He also requested the Department of Ethnic Minorities and Religions to grasp, advise, organize inspections, and urge the People's Committees of communes and wards to implement the contents that can be disbursed; the Department of Education and Training to urgently handle problems related to investment in facilities and equipment for schools; the Provincial Construction Investment Project Management Board to coordinate with departments, branches, and commune-level People's Committees to implement the projects received after implementing the 2-level local government model, ensuring completion in 2025; the Department of Construction to quickly complete the appraisal and approval process for adjusting the feasibility study report on construction investment, the technical and economic reports on construction of projects using public investment capital and foreign capital, and submit them to the Provincial People's Committee before October 3...