Concentrating efforts to complete the 500 kV circuit 3 line

Việt NamViệt Nam19/04/2024

In just over 2 months, the 500 kV line project, circuit 3, from Quang Trach ( Quang Binh ) to Pho Noi (Hung Yen) will reach its operational destination. Investors, contractors and material suppliers are focusing on implementing construction on the entire route. On the two project sections, the 92 km long Quynh Luu - Thanh Hoa 500 kV line and the 74.4 km long Thanh Hoa - Nam Dinh 1 Thermal Power Plant 500 kV line, construction work is being carried out simultaneously at 248/380 column foundation locations, to organize wire pulling construction at the end of April 2024.

Concentrating efforts to complete the 500 kV circuit 3 line

On the entire 500 kV transmission line in Thanh Hoa, 48 steel poles are currently being installed. Each pole weighs hundreds of tons of steel.

Concentrating efforts to complete the 500 kV circuit 3 line

Contractor workers - PC1 Group erecting steel pole at position 90 in Ba Dinh commune (Nga Son). This is one of 18 positions of package 40 - the first package in the entire 500 kV line 3 project to complete the foundation casting the earliest. The contractor is making efforts to deploy the construction, striving to complete the pole erection before May 10, then will proceed to pull the wire.

Concentrating efforts to complete the 500 kV circuit 3 line

The first column positions of package No. 40 have been completed, passing through the communes of Nga Thien, Nga Truong, Nga Van, Ba Dinh, Nga Thang (Nga Son). This package was handed over on December 12, 2023. With the support of local authorities, the close direction of Vietnam Electricity Group and the National Power Transmission Corporation, along with the efforts and reasonable construction organization measures of the construction unit, PC1 Group, the package was completed ahead of schedule.

Concentrating efforts to complete the 500 kV circuit 3 line

Representatives of the Advance Team 1 of the Northern Power Project Management Board and the contractor's leaders are regularly on site to urge and supervise the construction of the 500 kV Thanh Hoa - Nam Dinh 1 Thermal Power Plant line sections.

Concentrating efforts to complete the 500 kV circuit 3 line

Part of the 500 kV line 3 project, Thanh Hoa - Quynh Luu section, package 10 is one of the most difficult packages. All construction sites are located on mountain ranges in Truong Lam commune (Nghi Son town) and Quynh Vinh commune (Hoang Mai town).

Concentrating efforts to complete the 500 kV circuit 3 line

The contractor - Alphanam E&C Joint Stock Company had to open a new temporary road of more than 5 km through the forest to reach the foundation position of column No. 36 in Truong Lam commune (Nghi Son town). Along with that, due to the complex geology of the foundation position and hard rock, the contractor had to mobilize many special machines and equipment to carry out the construction.

Concentrating efforts to complete the 500 kV circuit 3 line

The 500 kV line circuit 3, Thanh Hoa - Quynh Luu section passes through 5 communes of Nghi Son town: Truong Lam, Tan Truong, Phu Lam, Phu Son and Cac Son with 43 column foundation locations. The total affected area is 58.67 hectares involving 138 households and 6 organizations.

Concentrating efforts to complete the 500 kV circuit 3 line

Due to the large construction volume and complex terrain, Nghi Son town authorities have promoted and mobilized people to lend the contractor forestry land to open many roads to bring machinery and equipment to the construction site.

Concentrating efforts to complete the 500 kV circuit 3 line

As of April 16, on the entire line 2 of the 500 kV line 3 project passing through Thanh Hoa province, contractors have completed casting foundations at 248/380 locations, erected 48 steel columns and are in the process of erecting 49 steel columns.

Concentrating efforts to complete the 500 kV circuit 3 line

More modern machines are continuing to be mobilized to Thanh Hoa (in photo: Robot pile driving to construct column foundations in Dai Loc commune (Hau Loc).

Concentrating efforts to complete the 500 kV circuit 3 line

Local authorities are continuing to mobilize people to agree and hand over the site of the corridor as soon as possible. Up to now, Thanh Hoa province has handed over 100% of the site of the column foundation construction site and 87/137 anchorage spaces of the corridor to the construction unit.

Concentrating efforts to complete the 500 kV circuit 3 line

Mr. Vo Cong Tai, Deputy Head of the Frontline 1, Northern Power Project Management Board, said: "The entire construction site is accelerating the foundation casting, organizing construction in 3 shifts and 4 teams. For the positions where the foundation has been completed, the columns are being erected simultaneously. At this time, we are constantly monitoring the construction site, urging contractors to focus on human and material resources, speeding up the construction progress to meet the planned milestones."

Minh Hang


Source

Comment (0)

No data
No data

Same tag

Same category

Lost in cloud hunting in Ta Xua
Admiring Gia Lai coastal wind power fields hidden in the clouds
Coffee shops in Hanoi are bustling with Mid-Autumn Festival decorations, attracting many young people to experience
Vietnam's 'sea turtle capital' recognized internationally

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product