Provincial Party Committee member, Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha spoke at the meeting. Photo: Hoang Loc |
However, the site clearance work is still facing many difficulties and obstacles, affecting the construction progress. Specifically, the Hieu Liem bridge project has started construction since the end of 2024, but up to now, there is still no construction site for the approach roads at both ends of the bridge, which is at risk of delaying the completion progress and directly affecting the plan for transporting materials and equipment for the main construction project.
EVN Deputy General Director Pham Hong Phuong reports on site clearance problems of the project. Photo: Hoang Loc |
Based on the above reality, EVN recommends that the Provincial People's Committee direct the People's Committee of Tri An commune to mobilize households cultivating on public land to agree to hand over the land. In case of non-compliance, coercive measures will be considered according to regulations. At the same time, the locality needs to urgently determine the origin of the land, develop and approve compensation, support and resettlement plans to pay and hand over the land for the project, especially the land for the road section at both ends of Hieu Liem bridge which is urgently needed.
Representative of Tri An commune reported difficulties and problems in determining the origin of land. Photo: Hoang Loc |
The provincial leaders requested the People's Committee of Tri An commune to establish a team to confirm the land origin based on reality to ensure the rights of the people in land acquisition. Mobilize the people to agree on the policy of handing over the site. Approve compensation and support plans before September 20.
The Tri An Hydropower Plant Expansion Project held a groundbreaking ceremony on August 19, 2025. Photo: Hoang Loc |
This hydroelectric plant has been in operation since 1991, consisting of 4 units, total capacity of 400 MW; average electricity output of about 1.76 billion kWh/year. This is a strategic hydroelectric project, both generating electricity and participating in flood regulation, supplying water for daily life and production for the downstream area.
Hoang Loc
Source: https://baodongnai.com.vn/kinh-te/202509/tang-cuong-nhan-su-choxa-tri-an-giai-phong-mat-bang-du-an-trong-diem-quoc-gia-nganh-nang-luong-4240ac0/
Comment (0)