Construction of Cay bridge reached 30% of volume

Việt NamViệt Nam21/04/2024

image(1).png
Beam casting construction at Cay bridge construction investment project. Photo: THANH CHUNG

The unit mobilized about 50 workers and more than a dozen machines and equipment, divided into construction teams for the river items and casting Super - T beams.

Cay Bridge connects Cam Dong commune (Cam Giang) and Hung Thang commune (Binh Giang). The project is invested by the Provincial Construction Investment Project Management Board.

The scale of the construction project is a level II plain road. The design speed is 80km/h. The bridge is built permanently with prestressed reinforced concrete, the width of the bridge is 30m, divided into 2 separate bridge units. The total length of the bridge is 182m with 4 spans of Super-T girders.

The construction contractor is the Hai Duong Irrigation Joint Venture – Licogi 18 – Bao Long. The construction supervision contractor is Thang Long Construction Quality Supervision Consulting Joint Stock Company.

The project will be implemented from March 20, 2024, with construction time of 390 days.

The investor requested the People's Committee of Binh Giang district to urgently complete site clearance and resettlement arrangements for households subject to resettlement... to ensure project construction progress.

Hanoi

Source

Tag: Cau Cay

Comment (0)

No data
No data

Same tag

Same category

Visit Lo Dieu fishing village in Gia Lai to see fishermen 'drawing' clover on the sea
Locksmith turns beer cans into vibrant Mid-Autumn lanterns
Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;