Minister of Planning and Investment inspects progress of coastal road section through Nghe An

Việt NamViệt Nam09/12/2024


This evening, the working delegation of Minister of Planning and Investment Nguyen Chi Dung inspected the progress of the coastal road from Nghi Son - Thanh Hoa to Cua Lo - Nghe An . Also traveling on the side of Nghe An province were comrades Nguyen Duc Trung - Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Le Hong Vinh - Member of the Provincial Party Committee Standing Committee, Permanent Vice Chairman of the Provincial People's Committee; leaders of relevant departments, branches, sectors and localities.

Minister of Planning and Investment Nguyen Chie Dung and his delegation inspected the progress of the Nghe An coastal road project.
Minister of Planning and Investment Nguyen Chi Dung and his delegation inspected the progress of the Coastal Road section through Nghe An.

The coastal route from Nghi Son ( Thanh Hoa ) to Cua Lo (Nghe An) from Km7 - Km76 was implemented from February 2022 on a length of nearly 60km. The total investment of the project is 4,651 billion VND, of which the construction part is over 3,200 billion VND.

To date, site clearance work has reached 98.2%. The entire project has disbursed nearly VND 3,440 billion, of which the construction part of both packages has disbursed nearly VND 2,460 billion, reaching 88%. In 2024 alone, VND 798.6 billion has been allocated and to date the disbursement rate has reached 76.65%.

Project
Site clearance work in Nghe An province has so far reached 98.2%.

According to the contract, the project will not be completed until February 2026. However, Nghe An province is directing and urging construction units to focus on human resources and equipment to speed up progress and strive to complete the project by mid-2025, 6 months ahead of schedule.

Director of Department of Transport reports on project progress.
Director of Department of Transport Hoang Phu Hien reports on project progress.

Reporting to the working group of the Ministry of Planning and Investment at the Lach Quen bridge in Quynh Luu district, the leader of the Department of Transport said that currently, 4/8 rigid bridges have been completed along the entire route. Construction units strive to complete the bridge section before January 2025; the roadbed before April 30 of next year.

For the 1km of land that is still stuck at some points, due to the involvement of 49 households, the localities are completing the procedures, paying the people and are expected to complete it by February next year.

Minister of Planning and Investment Nguyen Chi Dung directed at the scene.
Minister of Planning and Investment Nguyen Chi Dung directed at the scene.

Emphasizing the importance of the coastal route, Minister Nguyen Chi Dung suggested: From now on, Nghe An province needs to direct the localities where the coastal route passes through to protect the current status on both sides of the route; not to encroach or destroy the planning; prepare the conditions for a systematic planning in the future, opening up new spaces for the coastal economic development of Nghe An.

Provincial Party Secretary, Chairman of the Provincial People's Committee Nguyen Duc Trung spoke.
Provincial Party Secretary, Provincial People's Committee Chairman Nguyen Duc Trung spoke.

Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee Nguyen Duc Trung said: This issue has been directed by the provincial leaders and required local authorities to strictly implement; at the same time, he affirmed that the province will be determined and strive to complete the project as committed, soon put the project into operation, serving the socio-economic development requirements of Nghe An province./.

The Sun - Epic Song


Source: https://www.truyenhinhnghean.vn/thoi-su-chinh-tri/202412/bo-truong-bo-kh-dt-kiem-tra-tien-do-duong-ven-bien-doan-qua-nghe-an-5194625/

Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;