Speed ​​up project progress in the spirit of "construction begins as soon as the site is available"

DNO - On July 10, speaking at the inspection of the Quang Da Bridge project and the bridge approach road and the Northern beltway project, alternate member of the Party Central Committee, Deputy Secretary of the City Party Committee, Chairman of the People's Committee of Da Nang City Luong Nguyen Minh Triet directed that construction should be carried out as soon as the site is available to speed up the progress of the projects.

Báo Đà NẵngBáo Đà Nẵng10/07/2025

img_7575.jpg
Chairman of the City People's Committee Luong Nguyen Minh Triet delivered a concluding speech at the meeting. Photo: XUAN HAU

According to Chairman of the City People's Committee Luong Nguyen Minh Triet, the on-site inspection aims to confirm the urgency of the projects for the overall development of Da Nang City. At the same time, it demonstrates political determination in accelerating construction progress, completing projects soon, creating new development momentum, and effectively resolving the disbursement of central capital.

The Chairman of the City People's Committee requested the Party Committee and People's Committee of Dien Ban Bac Ward, together with relevant departments, branches and units, to focus on developing a detailed plan for compensation and site clearance, urgently coordinate to soon have a plan on prices and compensation for households, especially prioritizing site clearance at bridge and culvert locations, and curbs to create favorable conditions for contractors to construct.

Along with that, it is recommended to unify the policy of transferring the project in accordance with legal regulations, focusing on implementing resettlement projects in the immediate future. Regarding legal problems related to land and land consolidation, it is necessary to urgently handle them according to the old regulations of the People's Committee of Quang Nam province (old). Problems beyond the ward's authority must be reported to the City People's Committee for timely direction.

triet3.jpg
Chairman of the City People's Committee Luong Nguyen Minh Triet inspected the Quang Da Bridge project and the bridge approach road. Photo: XH

The Chairman of the City People's Committee directed the Department of Construction to support the ward in shortening the preparation time for construction to the maximum, ensuring that the project must start no later than October 2025. At the same time, review related resettlement projects to solve housing problems for affected people.

In addition, the Chairman of the City People's Committee requested the Management Board, investors, and the Department of Finance to study the plan to transfer part of the capital to other projects, and advise on a plan to extend the project disbursement time until 2026.

The City People's Committee assigned the Department of Home Affairs and the Department of Agriculture and Environment to urgently complete legal procedures related to the City Land Fund Development Center; review construction material mines (soil, sand, gravel), and promptly resolve investor proposals to ensure materials for construction.

The city leaders noted that the Construction Investment Project Management Board should coordinate with contractors and relevant agencies to work with the Central Government to resolve legal procedures related to railway overpasses and highway overpasses, promptly removing legal bottlenecks.

In particular, the Chairman of the City People's Committee emphasized the spirit of "construction as soon as the site is available", absolutely not waiting for the entire site to be completed before starting construction, to avoid prolonging the progress. Contractors must make detailed weekly construction plans, detailed monthly disbursement plans, and closely coordinate with supervision consultants and investors to check and evaluate specific responsibilities.

Contractors need to proactively remove difficulties in materials, vehicles, and human resources to speed up progress, especially the bridge project, to increase the capital disbursement rate.

img_7570.jpg
Working session scene. Photo: XUAN HAU

According to the report at the meeting, the Quang Da Bridge and approach road project started on December 21, 2023, and is expected to be completed on May 14, 2025. However, due to the incomplete clearance of households facing National Highway 14B, the City People's Committee has issued an official dispatch extending the construction period to December 31, 2025. Currently, there are two households facing National Highway 14B who have not agreed to hand over the land and 12 other households have signed the handover but have not yet started construction because they are requesting support.

According to Document No. 2034/UBND-BGPMB of the People's Committee of Hoa Vang District (old), the deadline for completing the site clearance work is before July 31, 2025. The contract value is more than 219.72 billion VND. The construction volume reached 97% of the contract value, of which the bridge part is 100% completed, while the access road, drainage, residential crossroads, and irrigation ditches on the main route have been completed. In particular, the area connecting to the National Highway 14B intersection is waiting for the site, some items need to be coordinated with the National Highway 14B renovation and upgrade project for synchronous implementation.

For the Northern Ring Road project, previously invested by the People's Committee of Dien Ban town (old), the total investment is 498 billion VND, using an area of ​​18.43 hectares, route length 4.62 km, implemented from 2022 to 2025. Compensation and site clearance work in Dien Hoa commune (old) has completed the first payment with a value of more than 2.83 billion VND for 25 households, area of ​​8,817.6 m²; the second payment is nearly 4.18 billion VND for 37/56 households, area of ​​16,244.8 m²; the residential land of 4 households affected is about 0.3 ha.

Compensation and site clearance work in Dien Tien commune (old), the first compensation plan has paid more than 873.86 million VND to 12 households, area 7,320.9 m²; the second payment of more than 16.4 billion VND to 142/143 households, area 52,515.4 m²; the third payment of more than 3.91 billion VND to 82/85 households, area 25,446.6 m². However, there are still about 2.46 hectares of land whose origin has not been determined because previously Dien Tien commune carried out field renovation, land consolidation and plot exchange but has not completed the procedures for adjusting land records and land use right certificates. In addition, the residential land affected 84 plots of land, which have been inventoried for households affected by a part of the area, and about 40 households subject to temporary clearance have not yet made a plan due to lack of resettlement land fund.

Source: https://baodanang.vn/day-nhanh-tien-do-cac-du-an-tren-tinh-than-co-mat-bang-toi-dau-thi-cong-toi-do-3265411.html


Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;