According to the Safety Department (Ha Tinh Electricity Company), immediately after the storm passed, the company mobilized maximum human resources and equipment to urgently fix the power grid problem.
By 7:00 a.m. on September 30, 2025, the whole province had restored 18/19 110kV lines (line 171 Can Loc to 171 Nghi Xuan did not affect the power outage at the 110kV station); 13/13 110kV substations; 28/88 line routes (32%); 2,204 substations (42%).
Up to now, 219,156 customers have had electricity (accounting for 44% of customers) in 49 wards and communes.

Currently, 34/69 wards and communes have been fully electrified, 15 wards and communes have been partially electrified.
Since September 29, Ha Tinh has received 512 officials and employees from 9 power companies including: Thai Nguyen, Dien Bien, Son La, Bac Ninh , Lai Chau, Hai Phong, Gia Lai, Dak Lak, Khanh Hoa and the Northern Power Service Company in the area of 8 power management teams to participate in support. Thanks to that, the work of overcoming power problems after the storm has been accelerated.
Source: https://baohatinh.vn/50-khach-hang-ha-tinh-duoc-cap-dien-tro-lai-post296535.html
Comment (0)