image001 (2).jpg
Photo: Nguyen Hue

Nhon Trach Bridge is located on Ring Road 3, with a total length of about 8.22km (including 6.3km passing through Dong Nai province and 1.92km passing through Ho Chi Minh City). Up to now, the construction progress of Nhon Trach Bridge construction package, cumulative output has reached 76% of the contract value, exceeding the proposed progress by 11%.

image003 (2).jpg
The main bridge section was completed and the three middle pillars were joined in September 2024. Photo: Nguyen Hue
image005 (1).jpg
The approach bridge has completed 34/36 piers and piers, reaching 95%; the installation of girders and concrete of the bridge deck has completed 21/34 spans, reaching 62%. Photo: Nguyen Hue
image007.jpg
Many workers were arranged to work in shifts day and night, including weekends and holidays, so that the construction could be completed earlier than expected. Photo: Nguyen Hue
image009.jpg
For the construction package of the approach road, 85% of the cement piles have been constructed. 76% of the roadbed sand has been filled; 33.34% of the crushed stone has been mixed. Photo: Nguyen Hue
image011.jpg
Photo: Nguyen Hue

According to the plan, contractors will construct the bridge deck, asphalt concrete pavement, lighting system, traffic safety to complete the entire component project 1A by April 2025.

image013.jpg
Photo: Nguyen Hue

When completed, the project will contribute to shortening the time and creating favorable conditions for travel from Nhon Trach district (Dong Nai) to Ho Chi Minh City and Binh Duong , enhancing the connectivity of satellite cities, expanding the space for developing land funds, services, trade, industry, logistics... for provinces and cities in the region.

In particular, the project contributes to remote traffic diversion and congestion reduction for inner-city routes in Ho Chi Minh City, gradually contributing to the completion of Ho Chi Minh City Ring Road 3.

Nguyen Hue