Gia Lai warns of sluggish progress of Nhon Hoi New City project

On September 11, the leader of Gia Lai Provincial People's Committee said that the Chairman of the Provincial People's Committee has just directed the Provincial Economic Zone Management Board to regularly inspect and urge enterprises, requesting to speed up the progress of subdivisions 2, 4 and 9 of Nhon Hoi New City Ecological Urban Area.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng11/09/2025

According to the Provincial Economic Zone Management Board, these three subdivisions have a total area of ​​about 116 hectares, planned for urban residential land and high-end coastal apartments, with Phat Dat Real Estate Development Joint Stock Company as the investor and Danh Khoi Holdings Investment Joint Stock Company as the developer.

ben-trong-khu-do-thi-nghin-ty-dong-o-binh-dinhdoan-cong-2jpgjpg-1749187209993.jpg
Gia Lai province continues to issue documents urging the Nhon Hoi New City project to urgently overcome existing problems and speed up the project as committed.

However, over the years, the project has been slow to implement, and there have been continuous complaints from people who have signed sales and transfer contracts but have not been granted land use right certificates, negatively affecting the province's investment environment.

Implementing the direction of the Provincial People's Committee Chairman, the Economic Zone Management Board requested the two enterprises to urgently focus resources: firstly, complete the power supply infrastructure in Sub-zone 2; power supply and wastewater collection system in Sub-zone 9; at the same time, maintain and repair degraded items, complete legal documents and financial obligations.

At the same time, businesses must promptly issue land use right certificates to customers who have paid 95%-100% of the contract value, and organize direct dialogues to resolve complaints. The deadline for completion is before September 30.

z7000035729297_35f41c5b88e7c0335813cc14fe619112.jpg
After many years of implementing and trading real estate products, Nhon Hoi New City subdivisions are still deserted.

The Economic Zone Management Board also requested the two companies to have a written commitment to progress and send notices to all customers to reassure public opinion and avoid large gatherings that could cause insecurity and disorder in the locality.

z7000038686249_670ac6d02883ab2b44bb264bbbb61a2e.jpg
Subdivision No. 2, area of ​​more than 36 hectares, more than 7,100 billion VND, deserted in the middle of the sand

Nhon Hoi New City project, with a total initial announced investment capital of more than 23,000 billion VND, is located on the coast of Phuong Mai peninsula, right on the front of National Highway 19B connecting Phu Cat airport, Cat Tien new urban area and Quy Nhon city.

z7000136349199_84afffff8e69de9a788f12f42bdfdd7b.jpg
Ky Co Gateway Area - Sub-area 9 has an area of ​​nearly 46 hectares, with a total investment of more than 8,500 billion VND.

Once causing a "virtual fever" for tourist land, after more than 6 years, the project is still deserted, with degraded infrastructure and lack of electricity and water, causing many customers to be upset and continuously send petitions to the authorities.

Source: https://www.sggp.org.vn/gia-lai-canh-bao-tien-do-i-ach-cua-du-an-nhon-hoi-new-city-post812564.html


Comment (0)

No data
No data

Same tag

Same category

The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.
Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;