In Hai Ninh ward, storm No. 10 caused serious damage. In addition to the tree system being broken and many houses being damaged, the most serious thing in the area was that many electric poles were broken and crooked.

Medium voltage power pole broken across traffic.

Broken down into the pond.
According to a quick report from Ha Tinh Electricity Company, due to the impact of storm No. 10, early this morning (September 29), the entire power grid system in the province was completely out of power.
Since early morning, leaders of Ha Tinh Electricity Company have inspected the power grid system, key locations and areas; directed power management units to urgently inspect and count the damage; and proactively deploy solutions to overcome the incident so that power can be restored as soon as safety conditions are met.


By 9:30 a.m., the company had restored 7/19 110kV lines; 5/13 110kV substations (Thach Linh, Ha Tinh, Cam Xuyen, Ky Anh 2, Nghi Xuan). However, due to the serious impact after the storm, 100% of the medium voltage lines have not been restored; 4,212 substations and 493,074 customers have lost power. In Thanh Sen ward and some neighboring areas, Ha Tinh Electricity is striving to restore power by noon today to serve the people, especially for the upcoming 20th Provincial Party Congress.

Power lines blocked the road, making it impossible for vehicles to pass.


The government and functional forces are reviewing the number of broken electric poles to soon have a solution to fix them.
Also according to information from the electricity industry, on the morning of September 29, 350 officers and technical workers from 5 power companies: Son La, Dien Bien, Lai Chau, Bac Ninh and Thai Nguyen are on their way to Ha Tinh to support the quick recovery of the power grid. It is expected that this afternoon, the units will approach the area, making efforts with the Ha Tinh electricity industry to restore the power grid as soon as possible.

This morning, due to the direct impact of storm No. 10, the 500kV line had an incident. Immediately after the incident occurred, the operating management units urgently mobilized forces and equipment to focus on handling the incident. Up to now, the locations where the incident occurred have been basically restored, the power transmission system has been restored and is ready to supply electricity.