Khanh Hoa criticized 16 units for disbursing investment capital too slowly.

Báo Tuổi TrẻBáo Tuổi Trẻ27/08/2024


Khánh Hòa phê bình 16 đơn vị giải ngân vốn đầu tư quá chậm - Ảnh 1.

The Cai River Nha Trang saltwater intrusion dam project is invested by public investment capital of Khanh Hoa province - Photo: PHAN SONG NGAN

According to the People's Committee of Khanh Hoa province, as of July 31, the disbursement rate of public investment capital in 2024 of the province only reached 24.5% compared to the capital plan assigned by the Government, lower than the national average (estimated at 32.2%).

Khanh Hoa Provincial People's Committee has issued a document criticizing 16 investment units with very low public investment disbursement results. Of which, 6 units had a public investment disbursement rate of less than 10% in the first 7 months of the year, including: Nha Trang College of Technology (0.6%), Department of Information and Communications (0.9%), Khanh Hoa University (1.1%), Department of Tourism (3.3%), Provincial Military Command (9.4%) and Van Phong Economic Zone Management Board (9.8%).

The remaining 10 criticized units include: Department of Transport (14.5%), Management Board of Investment Projects for Construction of Traffic Works (15.4%), People's Committee of Truong Sa District (15.8%), Management Board of Investment Projects for Construction of Agricultural Works and Rural Development (16.1%), Department of Agriculture and Rural Development (16.5%), Provincial Police (17.8%), Department of Construction (20.8%), Khanh Hoa Irrigation Works Exploitation Company Limited (24.3%), Cam Ranh City People's Committee (25.5%) and Tram Huong Forestry Company Limited (26.5%).

The head of the unit must be responsible to the Chairman of Khanh Hoa province.

According to the People's Committee of Khanh Hoa province, in the coming time (September 2024), if the criticized units do not improve the disbursement rate of public investment capital and do not ensure that the disbursement rate in 2024 reaches 95% or more as directed by the Prime Minister, the head of that agency or unit must be responsible to the Chairman of the Provincial People's Committee for not completing the disbursement plan in 2024.

The basis for the above assessment is the decision of Khanh Hoa Provincial People's Committee issued on the set of criteria for assessing and classifying the level of completion of the task of disbursing public investment capital plans in the province.



Source: https://tuoitre.vn/khanh-hoa-phe-16-don-vi-giai-ngan-von-dau-tu-qua-cham-20240827160001631.htm

Comment (0)

No data
No data

Same tag

Same category

Admiring Gia Lai coastal wind power fields hidden in the clouds
Coffee shops in Hanoi are bustling with Mid-Autumn Festival decorations, attracting many young people to experience
Vietnam's 'sea turtle capital' recognized internationally
Opening of the art photography exhibition 'Colors of life of Vietnamese ethnic groups'

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product