The route from Hoa River Bridge to Provincial Road 354 faces the risk of slow progress.

According to plan, the project to renovate the road section from Hoa River Bridge to Provincial Road 354 will be put into use by next December, but due to land acquisition problems, slow construction has led to the risk of the project being behind schedule.

Báo Hải PhòngBáo Hải Phòng05/09/2025

flower-road-2.jpg
Narrow space and heavy traffic make construction work difficult.

Lack of space

After the Hoa River Bridge connecting Vinh Am Commune (formerly Vinh Bao District) and Hung Yen Province (formerly Thai Thuy District, Thai Binh Province) was put into use in December 2019, the traffic volume from Hoa Bridge to Provincial Road 354 increased dramatically. Traffic jams often occur on the route, especially during rush hours. In this situation, the City People's Committee added a project to renovate and upgrade a 1.65 km section from Hoa River Bridge to Provincial Road 354, with an investment capital of 65.5 billion VND. After renovating and upgrading the route, it will meet the standards of a grade 3 delta road. The project started in November 2024 and is expected to be completed in December 2025.

However, due to many reasons, the project has only achieved 21% of the planned workload. Mr. Dinh Dac Phuong, Site Manager of Xuan Thanh Development Company Limited (the construction unit) said: the site was handed over in a "sticky rice and bean" manner, so the contractor encountered many difficulties in deploying machinery, equipment, and gathering materials. Having to construct in cramped conditions while ensuring traffic safety became a big challenge for the contractor. Due to the impact of storm No. 5, the construction progress was also affected.

To serve the construction, the project reclaimed 3.71 hectares of land related to 235 cases. However, up to now, 29 households and 1 organization have not yet handed over the land.

flower-road-1.jpg
There are 29 households with land within the project area that have not agreed to hand over the site, putting the project at risk of being behind schedule.

Need to focus on synchronizing solutions

The representative of the Hai Phong Traffic and Agricultural Construction Project Management Board (the project investor) said: the 1.65 km road section connecting Hoa River Bridge to Provincial Road 354 before being renovated and upgraded was like a "bottleneck", greatly affecting the traffic flow and the risk of collisions and traffic accidents was very high. The early completion of the project will contribute to solving the above situation and synchronously exploiting Provincial Road 354 and Hoa River Bridge.

Mr. Dinh Dac Phuong, Construction Site Manager of Xuan Thanh Development Company Limited, shared that the contractor wanted to increase the number of shifts, mobilize vehicles and workers for construction, but encountered many difficulties because the site was not fully handed over. During rush hour, the number of trucks, buses and workers passing through this route increased, making construction impossible...

In early September, if Vinh Am commune does not mobilize and enforce land acquisition for 29 households to hand over the site to the construction contractor, the project will be behind schedule. The route passes through a densely populated area, and the construction also involves moving underground systems such as: electric cables, water pipes, telecommunication cables... Not to mention the disadvantages of the weather.

The project to renovate and upgrade the road connecting Hoa River Bridge to Provincial Road 354 is not long, the investment is not large, but it has an important meaning in connecting and organizing traffic. But up to now, the unfinished project is becoming a source of frustration for people who participate in traffic through this area every day and for local people.

To speed up the progress, the People's Committee of Vinh Am commune needs to urgently and resolutely clear the site. The investor should strengthen inspection and review of the implemented volume, build detailed progress by week and month; direct the contractor to concentrate resources, add construction teams, organize "3 shifts, 4 teams" to compensate for the slow volume and ensure the completion of the remaining items in December 2025.

PHAM CUONG

Source: https://baohaiphong.vn/tuyen-duong-tu-cau-song-hoa-den-duong-tinh-354-doi-mat-nguy-co-cham-tien-do-519893.html


Comment (0)

No data
No data

Same tag

Same category

Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory
Tò he – from a childhood gift to a million-dollar work of art

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;