Removing obstacles and promoting progress of industrial parks

Large industrial park (IP) projects in Lam Dong are in the implementation phase but are facing many difficulties. The Provincial People's Committee has directed relevant departments and branches to join in resolving them.

Báo Lâm ĐồngBáo Lâm Đồng12/08/2025

Tan Duc Industrial Park in Tan Minh commune has a scale of 300 hectares, currently 281.9 hectares have been cleared, reaching 97.53%. The Provincial People's Committee has leased land in 3 phases, with a total area of ​​288.5 hectares, reaching 96.1% of the scale of the Industrial Park. The construction of technical infrastructure in phase 1 has reached about 90% of the volume, the value implemented in 7 months of 2025 is 273.5/562 billion VND, the cumulative amount is 900.2/1,200 billion VND, equivalent to 75.02% of the total registered investment capital. However, there are still 33 dossiers with 7.3 hectares that have not had their compensation plan approved and the intersection of National Highway 1A with the Industrial Park has not been completed due to site clearance problems. The 110 kV power station serving the Industrial Park has not been deployed, causing concerns that it will affect the overall completion progress.

Tan Duc Industrial Park
Tan Duc Industrial Park in Tan Minh commune has cleared 281.9 hectares of land, reaching 97.53%. Photo: Ngoc Lan

Son My 1 Industrial Park (Son My Commune) has an area of ​​1,070 hectares, with a total registered capital of VND2,300 billion. Currently, compensation has only been carried out on 86.7 hectares, of which 76.5 hectares have been leased by the Provincial People's Committee. Notably, the priority area of ​​375 hectares has 288.5 hectares that have not been handed over, of which 7 organizations with 226.8 hectares have not agreed to receive compensation. With 65 households/45.32 hectares, although the compensation plan of VND81.3 billion has been approved, IPICO Joint Stock Company has not yet transferred the funds to the Land Fund Development Center...

Son My 2 Industrial Park Phase 1 with an area of ​​468.35 hectares and an investment capital of 1,717 billion VND is currently only at the stage of site clearance. Land acquisition, selection of a consulting unit to determine land prices and compensation plan development are still slow. The investor continues to review and complete the feasibility study report according to the appraisal opinion of the Department of Construction.

Faced with the above situation, Mr. Phan Duong Cuong - Head of the Provincial Industrial Park Management Board said that for Tan Duc Industrial Park, the Board is coordinating with Tan Minh commune to speed up the settlement of the remaining 33 files; coordinating with the Land Fund Development Center to complete related procedures to continue paying compensation; coordinating with the Department of Industry and Trade to work with the electricity industry to deploy the 110 kV station of Tan Duc Industrial Park in the fourth quarter of 2025. The Project Management Board is coordinating with the Department of Finance and localities to resolve the issue thoroughly, avoiding prolonging the impact on people's confidence and project progress. For Son My 2 Industrial Park Phase 1, with a scale of 468.35 hectares but implementation is still slow, the Board is coordinating with localities to develop a land recovery plan and determine land prices.

Mr. Cuong added that the Industrial Park Management Board will continue to closely monitor each project, regularly update progress and closely coordinate with localities and investors to remove difficulties.

At the meeting to resolve difficulties with the Management Board of Industrial Parks, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Hong Hai emphasized that departments, branches and localities need to coordinate closely to resolve problems at industrial parks regarding land prices, compensation, traffic infrastructure, electricity, etc. Specifically, the Department of Finance will arrange capital for infrastructure investment and resolve proposals on funding; the Department of Construction will coordinate in planning resettlement areas and workers' housing; the Department of Agriculture and Environment will handle problems with national defense land; the Tax Department of Region XIV will handle investment incentives, etc. People's Committees of localities with industrial parks must ensure site clearance and maintain security and order.

Regarding Tan Duc Industrial Park, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai requested to focus on site clearance, ensuring the completion of phase 1 of the project in September 2025; at the same time, closely coordinate with departments, branches and localities to remove obstacles regarding land prices, compensation, and connecting infrastructure. Regarding Son My 1 Industrial Park, urgently hand over the site of Son My I, Son My II projects and Son My LNG Warehouse, ensuring progress; at the same time, complete technical infrastructure items to attract investment. Regarding Son My 2 Industrial Park phase 1, speed up the infrastructure construction progress, completely resolve obstacles related to site clearance and traffic infrastructure, water supply, ensuring the best conditions for businesses to soon deploy operations.

Source: https://baolamdong.vn/go-vuong-mac-thuc-day-tien-do-cac-khu-cong-nghiep-387203.html


Comment (0)

No data
No data

Same tag

Same category

Lost in cloud hunting in Ta Xua
There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory
Tò he – from a childhood gift to a million-dollar work of art

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;